  "id": 6142389,
  "name": "NESTE POLYESTER, INC. v. Frank BURNETT, et al.",
  "name_abbreviation": "Neste Polyester, Inc. v. Burnett",
  "decision_date": "2005-10-05",
  "docket_number": "CA 04-1186",
  "first_page": "413",
  "last_page": "423",
  "citations": [
    {
      "type": "official",
      "cite": "92 Ark. App. 413"
    },
    {
      "type": "parallel",
      "cite": "214 S.W.3d 882"
    }
  ],
  "court": {
    "name_abbreviation": "Ark. Ct. App.",
    "id": 13370,
    "name": "Arkansas Court of Appeals"
  },
  "jurisdiction": {
    "id": 34,
    "name_long": "Arkansas",
    "name": "Ark."
  },
  "cites_to": [
    {
      "cite": "335 Ark. 470",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        862766
      ],
      "weight": 2,
      "year": 1998,
      "opinion_index": 0,
      "case_paths": [
        "/ark/335/0470-01"
      ]
    },
    {
      "cite": "354 Ark. 112",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        36051
      ],
      "weight": 2,
      "year": 2003,
      "opinion_index": 0,
      "case_paths": [
        "/ark/354/0112-01"
      ]
    },
    {
      "cite": "40 Ark. App. 172",
      "category": "reporters:state",
      "reporter": "Ark. App.",
      "case_ids": [
        6139583
      ],
      "weight": 2,
      "year": 1992,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/40/0172-01"
      ]
    },
    {
      "cite": "298 Ark. 78",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1889919
      ],
      "weight": 2,
      "year": 1989,
      "opinion_index": 0,
      "case_paths": [
        "/ark/298/0078-01"
      ]
    },
    {
      "cite": "252 Ark. 1223",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1630106
      ],
      "weight": 2,
      "year": 1972,
      "opinion_index": 0,
      "case_paths": [
        "/ark/252/1223-01"
      ]
    },
    {
      "cite": "770 N.E.2d 1068",
      "category": "reporters:state_regional",
      "reporter": "N.E.2d",
      "year": 2001,
      "opinion_index": 0
    },
    {
      "cite": "242 Ark. 817",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        8723997
      ],
      "weight": 2,
      "year": 1967,
      "opinion_index": 0,
      "case_paths": [
        "/ark/242/0817-01"
      ]
    },
    {
      "cite": "504 N.E.2d 415",
      "category": "reporters:state_regional",
      "reporter": "N.E.2d",
      "year": 1986,
      "pin_cites": [
        {
          "page": "418"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "16 Ark. App. 182",
      "category": "reporters:state",
      "reporter": "Ark. App.",
      "case_ids": [
        6655910
      ],
      "weight": 2,
      "year": 1985,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/16/0182-01"
      ]
    },
    {
      "cite": "275 Ark. 340",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1753671
      ],
      "weight": 2,
      "year": 1982,
      "opinion_index": 0,
      "case_paths": [
        "/ark/275/0340-01"
      ]
    },
    {
      "cite": "85 Ark. App. 443",
      "category": "reporters:state",
      "reporter": "Ark. App.",
      "case_ids": [
        6141759
      ],
      "weight": 3,
      "year": 2004,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/85/0443-01"
      ]
    },
    {
      "cite": "66 Ark. App. 220",
      "category": "reporters:state",
      "reporter": "Ark. App.",
      "case_ids": [
        6139831
      ],
      "weight": 2,
      "year": 1999,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/66/0220-01"
      ]
    },
    {
      "cite": "267 Ark. 841",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1719893
      ],
      "weight": 2,
      "year": 1980,
      "pin_cites": [
        {
          "parenthetical": "all holding that, while information disclosed during discovery is not a pleading or a defense to a pleading, such information may give rise to amendments to pleadings"
        },
        {
          "parenthetical": "all holding that, while information disclosed during discovery is not a pleading or a defense to a pleading, such information may give rise to amendments to pleadings"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ark/267/0841-01"
      ]
    },
    {
      "cite": "686 S.W.2d 808",
      "category": "reporters:state_regional",
      "reporter": "S.W.2d",
      "case_ids": [
        6140841,
        6140964
      ],
      "year": 1985,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/14/0215-01",
        "/ark-app/14/0217-01"
      ]
    },
    {
      "cite": "14 Ark. App. 217",
      "category": "reporters:state",
      "reporter": "Ark. App.",
      "case_ids": [
        6140964
      ],
      "year": 1985,
      "opinion_index": 0,
      "case_paths": [
        "/ark-app/14/0217-01"
      ]
    },
    {
      "cite": "247 Ark. 577",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1600548
      ],
      "weight": 2,
      "year": 1969,
      "opinion_index": 0,
      "case_paths": [
        "/ark/247/0577-01"
      ]
    },
    {
      "cite": "262 Ark. 773",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1675850
      ],
      "weight": 2,
      "year": 1978,
      "opinion_index": 0,
      "case_paths": [
        "/ark/262/0773-01"
      ]
    },
    {
      "cite": "247 Ark. 130",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1600701
      ],
      "weight": 2,
      "year": 1969,
      "opinion_index": 0,
      "case_paths": [
        "/ark/247/0130-01"
      ]
    },
    {
      "cite": "250 Ark. 1083",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1636881
      ],
      "weight": 3,
      "year": 1971,
      "opinion_index": 0,
      "case_paths": [
        "/ark/250/1083-01"
      ]
    },
    {
      "cite": "250 Ark. 1083",
      "category": "reporters:state",
      "reporter": "Ark.",
      "case_ids": [
        1636881
      ],
      "weight": 2,
      "year": 1971,
      "opinion_index": 1,
      "case_paths": [
        "/ark/250/1083-01"
      ]
    }
  ],
  "analysis": {
    "cardinality": 845,
    "char_count": 18497,
    "ocr_confidence": 0.775,
    "pagerank": {
      "raw": 5.507290070623438e-08,
      "percentile": 0.3443349399907099
    },
    "sha256": "0a25f471019d62c19f97ce4dcce11b22695a44deec4f0d03f13b2ad2be283a55",
    "simhash": "1:9e6246a53f289be0",
    "word_count": 3057
  },
  "last_updated": "2023-07-14T16:18:39.939690+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [
      "Vaught, J., agrees.",
      "Hart, J., concurs."
    ],
    "parties": [
      "NESTE POLYESTER, INC. v. Frank BURNETT, et al."
    ],
    "opinions": [
      {
        "text": "Olly Neal, Judge.\nThis appeal is from a jury verdict awarding appellees Frank Burnett and Dennis Joslin Company 2000, Inc., damages in the sum of $2,500,000 for breach of warranty on a defective product used to seal boats. Appellant Neste Polyester, Inc., raises four points concerning Viper\u2019s amendment of the complaint to conform to the proof, the trial court\u2019s striking of its affirmative defenses, the trial court\u2019s failure to submit the case to the jury on interrogatories, and the trial court\u2019s failure to award a new trial. Finding no error, we affirm.\nViper is a manufacturer of fiberglass recreational boats. Neste manufactures the clear coat Viper used to protect the finish of its boats. From June 1994 until April 1999, Viper purchased all of its clear coat from Neste. In April 1999, Neste informed Viper that all of its clear coat purchased since April 1998 was defective. Viper had manufactured 784 boats using the defective product and, by May 1999, had received twenty-seven complaints. Neste paid for the replacement of these twenty-seven boats. Viper thereafter determined that the only way to remedy the remaining defective boats was to replace them. Neste refused to pay for the replacement of the remaining boats.\nOn October 23, 2000, Viper filed suit against Neste alleging breach of express and implied warranties, negligence, breach of contract, and fraud. Viper alleged that Neste was liable for the replacement of all 784 boats and that its damages could exceed $10,000,000. In both the complaint and first amended complaint, Viper alleged that the problems with the clear coat threatened to destroy its business reputation and goodwill. Neste denied the allegations.\nAt a November 25, 2003, pre-trial conference, Viper\u2019s attorney disclosed its expert economist, Robert \u201cjay\u201d Marsh, and announced that Viper was pursing a new approach to damages. That approach was to seek damages for its loss of business and loss of future profits. Neste\u2019s then-attorney, Alfred Angulo, recognized that this announcement changed Viper\u2019s theory of the case and placed Neste on notice that Viper was seeking damages for the loss of its entire business. Angulo did not object to this change in theories, nor did he move for a continuance.\nFollowing the November conference, a scheduling order was entered providing that Viper was to amend its discovery responses so as to provide the substance of Marsh\u2019s opinion by February 5, 2004. Neste was to disclose its expert, together with the substance of its expert\u2019s testimony by March 8, 2004. Neste disclosed its expert, Richard Schwartz, after the deadline in the scheduling order and did not provide Schwartz\u2019s report. The scheduling order also provided that all exhibits and witness lists were to be exchanged by March 16, 2004. All motions, except for motions in limine, were to be filed by May 2, 2004, with all motions in limine filed by May 25, 2004.\nViper moved for partial summary judgment as to liability. After Neste failed to respond to the motion, an order was entered granting Viper summary judgment as to the issue of liability. The issue of damages was to be tried.\nLater, Viper timely moved for summary judgment on the issue of damages, alleging that, as a result of the problems with Neste\u2019s clear coat, Viper\u2019s business declined until Viper ceased operations in 2003. The motion was supported by Marsh\u2019s affidavit and report, stating that he had calculated Viper\u2019s economic loss at $6,452,259. This motion was denied.\nAfter the motion for summary judgment as to damages was denied, Neste filed a timely motion in limine seeking to prevent Marsh from testifying at trial because Marsh had no personal knowledge of the matter and because he was addressing a measure of damages that Neste alleged was improper and inapplicable. In an accompanying brief, Neste argued that the proper measure of damages was the difference in the fair market value of the business before and after the event. The court denied the motion.\nAt trial, Neste also made an oral motion seeking to limit Viper to the damages mentioned in its complaint and amended complaint, arguing that the lost profits discussed were not specifically pled by Viper. The trial court reserved ruling on the issue of the type of damages upon which it was going to instruct the jury and noted that Neste could object to evidence on the different types of damages.\nIn addition, during trial, Neste filed an answer to Viper\u2019s new claim for special damages, asserting that Viper had not pled the issue of special damages for lost profits, as required by Ark. R. Civ. P. 9(g). The answer also asserted other defenses such as release, limitation of damages pursuant to a clause in the invoices, improper party plaintiff, and failure to state a claim upon which relief can be granted. Viper moved to strike the answer as untimely. The trial court ordered the answer stricken.\nNeste sought to have the jury return a verdict on special interrogatories while Viper sought a general verdict. Neste\u2019s proffered instructions were as follows:\n3.Do you find that the defective gel clearcoat sold by Neste was the proximate cause of the demise of Viper Boats, Inc.? _YES _NO\n4.Do you find the plaintiff is entitled to recover from the defendant lost profits that may have been suffered by Viper Boats, Inc.? _YES _NO\n5. What amount of past lost profits, if any, do you determine the defendant should pay to the plaintiff because of the demise of Viper Boats, Inc.? $_\n6. What amount of future lost profits, if any, do you determine the defendant should pay to the plaintiff because of the demise of Viper Boats, Inc.? $_\nThe trial court decided without explanation to submit the case to the jury on a general verdict form. The trial court also instructed the jury that it should consider two elements of damage: the amount of lost profit, or economic loss, to Viper from any decline in sales and the cessation of its business; and the amount of loss in value of Viper\u2019s business assets due to its cessation of business.\nThe jury returned a general verdict in favor of Viper and awarded damages of $2,500,000. Judgment was entered on the jury\u2019s verdict on June 16, 2004. Neste timely filed a motion for judgment notwithstanding the verdict or a new trial, alleging that Viper failed to present legally sufficient evidence to support the damage award or to show a causal link between Neste\u2019s actions and Viper\u2019s lost profits or demise of its business. Although the motion for judgment notwithstanding the verdict was deemed denied as of July 30, 2004, the trial court entered an order denying the motion on August 4, 2004. This appeal followed.\nNeste raises four issues on appeal: (1) that the trial court erred in not requiring Viper to comply with Ark. R. Civ. P. 9(g) and in permitting Viper to present evidence concerning special damages that had not been raised in the pleadings; (2) that the trial court erred in granting Viper\u2019s motion to amend the pleadings to conform to the proof and in striking Neste\u2019s answer to the claim for special damages because the issue of special damages had not been raised by amendment to the complaint; (3) that the trial court erred in overruling Neste\u2019s objection to the general verdict form and refusing Neste\u2019s requested verdict on special interrogatories; (4) that the trial court cumulatively erred by refusing to grant Neste a new trial based on the error in instructing the jury, the jury\u2019s error in assessing the amount of recovery, and the irregularity resulting from Viper\u2019s change in theories without amendment to the complaint.\nIn its first point, Neste argues that the trial court erred in permitting evidence to be presented concerning Viper\u2019s lost profits because lost profits are special damages which Ark. R. Civ. P. 9(g) requires to be specifically pled and Viper did not comply with that requirement. We disagree.\nThe parties dispute whether Viper\u2019s lost profits were or were not special damages. However, we need not answer the questions of whether lost profits are special damages or whether Viper\u2019s complaint was sufficient to plead special damages because, assuming that lost profits are special damages, we hold that the parties tried the issue without objection and, thus, the complaint was properly amended to conform to the proof so as to allege special damages. The purpose of requiring special damages to be specifically pled is to avoid surprise at trial. Arkansas La. Gas Co. v. McGaughey Bros., Inc., 250 Ark. 1083, 468 S.W.2d 754 (1971); Arkansas State Highway Comm\u2019n v. Dixon, 247 Ark. 130, 444 S.W.2d 571 (1969). However, if there is no surprise to the defendant, evidence relating to the special damages may be introduced. McGaughey Bros., supra.\nWe hold that Viper substantially complied with Rule 9(g) because the pleadings were amended to conform to the proof by presenting Marsh\u2019s summary-judgment affidavit and trial testimony. In Harrington v. City of Greenbrier, 262 Ark. 773, 561 S.W.2d 302 (1978), the supreme court assumed, without having to decide, that a plaintiff could assert a new cause of action in his summary-judgment affidavit, without amending his complaint. See Bonds v. Littrell, 247 Ark. 577, 446 S.W.2d 672 (1969); National Sec. Fire & Cas. Co. v. Shaver, 14 Ark. App. 217, 686 S.W.2d 808 (1985); Miller v. Hardwick, 267 Ark. 841, 591 S.W.2d 659 (Ark. App. 1980) (all holding that, while information disclosed during discovery is not a pleading or a defense to a pleading, such information may give rise to amendments to pleadings).\nNeste failed to object to Marsh\u2019s testimony at any time on the basis that Viper had failed to specifically plead its lost profits. Neste\u2019s response to Viper\u2019s summary-judgment motion on damages did not indicate that the lost-profits issue was not properly pled. When Neste sought to prohibit Marsh\u2019s trial testimony through a motion in limine, its motion and supporting brief did not raise the issue of the lost profits not being properly pled. Instead, it merely questioned Marsh\u2019s qualifications. It was not until Neste\u2019s oral motion at trial seeking to limit Viper to the damages mentioned in its complaint and amended complaint that the issue of lost profits not being specifically pled by Viper was raised. However, the trial court allowed Marsh to testify and noted that Neste could object to evidence on the different types of damages. The result of the trial court\u2019s ruling was to require Neste to make a specific objection to Marsh\u2019s testimony at trial. See Casteel v. State Farm Mut. Auto. Ins. Co., 66 Ark. App. 220, 989 S.W.2d 547 (1999).\nAt trial, Neste objected when Marsh was tendered as an expert witness on the basis that he lacked the qualifications to testify as to any issue in the case. The trial court overruled the objection and qualified Marsh as an expert. Later, as Marsh was about to give his opinion on Viper\u2019s lost profits, Neste objected on the basis of \u201cthe same objection we made before the court before as to the appropriateness of this testimony and the measure of damages.\u201d The trial court overruled the objection, and Marsh proceed to give his opinion as to Viper\u2019s lost profits. The objection that was raised went to Marsh\u2019s qualifications as an expert and the appropriate measure of damages, i.e., whether the measure of damages is the difference in fair market value, not that the lost profits had not been specifically pled. Therefore, without the objection now being urged on appeal, the trial court could have, under Ark. R. Civ. P. 15(b), properly considered the pleadings as amended to conform to the proof. Moreover, there is no claim of surprise by Neste. In fact, Neste conceded at oral argument that it could not claim surprise, based on Angulo\u2019s statements at the November 2003 pre-trial conference. Permitting the introduction of proof on an issue not raised in the pleadings constitutes an implied consent to trial on that issue. Ison Props., LLC v. Wood, 85 Ark. App. 443, 156 S.W.3d 742 (2004). We will not reverse a trial court\u2019s decision regarding the amendment of pleadings to conform to the evidence in the absence of a manifest abuse of discretion. Id. Here, we cannot say that the trial court abused its discretion in this regard. Therefore, we affirm on this point.\nNeste next argues that it was prejudiced because the trial court refused to allow it to submit its affirmative defenses to Viper\u2019s evidence concerning lost profits. As noted above, Viper disclosed that it was seeking lost profits at a November 2003 pretrial hearing. Neste did not object or seek a continuance at that time. Rather, Neste waited until May 6, 2004, to move for a continuance and did not file its affirmative defenses until the day of trial. Any prejudice to Neste comes from its own failure to comply with the trial court\u2019s scheduling order and deadlines and not from any failure by Viper to properly plead that it was seeking lost profits. A trial court\u2019s decision regarding the striking of a pleading will not be reversed in the absence of an abuse of discretion. Ison Props., supra. We cannot say that the trial court abused its discretion by striking Neste\u2019s affirmative defenses first raised on the morning of trial.\nThe third issue is whether the trial court erred in rejecting Neste\u2019s request to submit the verdict on interrogatories to the jury. It is within the trial court\u2019s discretion whether to submit a case to the jury on a general verdict or on interrogatories. Ark. R. Civ. P. 49(a); Hough v. Continental Leasing Corp., 275 Ark. 340, 630 S.W.2d 19 (1982). The complaining party should show how the trial court abused its discretion in failing to submit the proposed interrogatories. National Sec. Fire & Cas. Co. v. Williams, 16 Ark. App. 182, 698 S.W.2d 811 (1985). The form of the special verdicts submitted to the jury is also within the trial court\u2019s discretion. See Ark. R. Civ. P. 49(b).\nThe trial court did not abuse its discretion in rejecting Neste\u2019s proffered special interrogatories. \u201cThe essential purpose to be served by interrogatories is to test the correctness of a general verdict by eliciting from the jury its assessment of the determinative issues presented by a given controversy in the context of evidence presented at trial.\u201d Cincinnati Riverfront Coliseum, Inc. v. McNulty Co., 504 N.E.2d 415, 418 (Ohio 1986); see also Argo v. Blackshear, 242 Ark. 817, 416 S.W.2d 314 (1967); David Newbern and John Watkins, Arkansas Civil Practice and Procedure \u00a7 25-3 (3d ed. 2002). Neste\u2019s proposed interrogatories did not address ultimate or determinative issues. The relevant ultimate or determinative issue is the amount of lost profits Viper suffered due to the defective clear coat. Neste, in effect, sought to have the jury \u201citemize\u201d those damages according to arbitrary dates. Such itemizations are not determinative and would not test the ultimate verdict in this case regarding the appropriateness of an award of lost profits. UZ Engineered Prods. Co. v. Midwest Motor Supply Co., Inc., 770 N.E.2d 1068 (Ohio App. 2001). Also, the interrogatories submitted omitted some of the elements of damage claimed by Viper. Like jury instructions, special interrogatories should accurately reflect the evidence and the damages claimed. McDaniel Bros. Const. Co. v. Mid-State Const. Co., 252 Ark. 1223, 482 S.W.2d 825 (1972); see also Pineview Farms, Inc. v. Smith Harvestore, Inc., 298 Ark. 78, 765 S.W.2d 924 (1989); Property Owners Improvement Dist. v. Williford, 40 Ark. App. 172, 843 S.W.2d 862 (1992).\nThe final issue raised by Neste is that it should be awarded a new trial because of the cumulative errors alleged in the first three points. We do not reach the merits of this cumulative-error argument, as Neste failed to make a cumulative-error objection below. The supreme court has previously held that an appellant asserting a cumulative-error argument must show that there were individual objections to the alleged errors and that the cumulative-error objection was made to the trial court and a ruling was obtained. Southern Farm Bureau Cas. Ins. Co. v. Daggett, 354 Ark. 112, 118 S.W.3d 525 (2003); Edwards v. Stills, 335 Ark. 470, 984 S.W.2d 366 (1998).\nAffirmed.\nVaught, J., agrees.\nHart, J., concurs.\nThe original plaintiff was Viper Boats, Inc. Viper\u2019s board of directors adopted a resolution calling for the execution of an assignment granting Burnett and Dennis Joslin Company 2000, Inc., all ofViper\u2019s right, title, and interest in the lawsuit. Thereupon,Burnett and Dennis Joslin Company 2000, Inc., were substituted as the real parties in interest. For convenience and clarity, we will refer to appellees as Viper.\nSuit was originally filed in Baxter County, Viper\u2019s principal place of business, and later transferred to Sebastian County, Neste\u2019s principal place of business.\nNeste also filed a third-party complaint against the manufacturers of one of the components of its clear coat. This third-party complaint was later voluntarily dismissed by Neste.",
        "type": "majority",
        "author": "Olly Neal, Judge."
      },
      {
        "text": "Josephine Linker Hart, Judge,\nconcurring. I agree that this case must be affirmed, but write separately because I respectfully disagree with the majority\u2019s analysis concerning Neste Polyester\u2019s argument that the trial court erred in admitting evidence concerning Viper\u2019s lost profits theory for recovery of damages because lost profits are \u201cspecial damages,\u201d and Viper failed to comply with Rule 9(g) of the Arkansas Rules of Civil Procedure that its damage theory be specifically pled. I cannot agree that Viper\u2019s pleadings \u201csubstantially complied\u201d with Rule 9(g), or that this point was somehow barred because he failed to object to Viper\u2019s expert testifying about lost profits. Neste\u2019s argument fails simply because it has long been settled law that the purpose of requiring special damages to be pled is to prevent surprise, and where no surprise is pleaded and no time requested to prepare to meet the issue, there is no error. Arkansas Louisiana Gas Co. v. McGaughey Bros., Inc., 250 Ark. 1083, 468 S.W.2d 754 (1971). At oral arguments, Neste stated unequivocally that it was not surprised by Viper\u2019s damage theory; therefore, there is no reversible error.\nI concur.",
        "type": "concurrence",
        "author": "Josephine Linker Hart, Judge,"
      }
    ],
    "attorneys": [
      "Wright, Lindsey &Jennings LLP, by: Troy A. Price, for appellant.",
      "Garvin, Agee, Carlton & Mashhurn, L.L.P., by: John Mashburn and Alan Agee; andJones & Harper, by: Robert L. Jones III, for appellees."
    ],
    "corrections": "",
    "head_matter": "NESTE POLYESTER, INC. v. Frank BURNETT, et al.\nCA 04-1186\n214 S.W.3d 882\nCourt of Appeals of Arkansas\nOpinion delivered October 5, 2005\nWright, Lindsey &Jennings LLP, by: Troy A. Price, for appellant.\nGarvin, Agee, Carlton & Mashhurn, L.L.P., by: John Mashburn and Alan Agee; andJones & Harper, by: Robert L. Jones III, for appellees."
  },
  "file_name": "0413-01",
  "first_page_order": 439,
  "last_page_order": 449
}