  "id": 2662676,
  "name": "Joseph Henry et al., Appellees, v. Samuel M. Miller, Appellant",
  "name_abbreviation": "Henry v. Miller",
  "decision_date": "1908-11-17",
  "docket_number": "",
  "first_page": "628",
  "last_page": "630",
  "citations": [
    {
      "type": "official",
      "cite": "145 Ill. App. 628"
    }
  ],
  "court": {
    "name_abbreviation": "Ill. App. Ct.",
    "id": 8837,
    "name": "Illinois Appellate Court"
  },
  "jurisdiction": {
    "id": 29,
    "name_long": "Illinois",
    "name": "Ill."
  },
  "cites_to": [
    {
      "cite": "233 Ill. 409",
      "category": "reporters:state",
      "reporter": "Ill.",
      "case_ids": [
        3379643
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ill/233/0409-01"
      ]
    }
  ],
  "analysis": {
    "cardinality": 298,
    "char_count": 5326,
    "ocr_confidence": 0.518,
    "pagerank": {
      "raw": 8.594203391136844e-08,
      "percentile": 0.4896105911966296
    },
    "sha256": "3ac4aa384f15c6891192e681c2cb9d00fa0df19159a1fddd44386e527cccd14e",
    "simhash": "1:eb566ea2ece70cc4",
    "word_count": 894
  },
  "last_updated": "2023-07-14T21:26:10.404962+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "Joseph Henry et al., Appellees, v. Samuel M. Miller, Appellant."
    ],
    "opinions": [
      {
        "text": "Mr. Justice Baume\ndelivered the opinion of the court.\nOn June 30, 1906, the appellant, Samuel M. Miller, leased to Louis J. Robertson certain lands and premises, including buildings, improvements and machinery, to be operated as a coal mine, for a term ending April 1, 1912. The lease provided that Robertson should put in a good boiler and electric bells within ninety days from the date thereof at his own expense, and also make any other improvements he might desire, such improvements to become the property of Miller at the expiration of the lease. The lease further provided that Robertson should have the privilege of purchasing the leased premises at any time during the life of the lease for the sum of $20,000 in cash. Robertson went into possession of the premises- under the lease and thereafter employed laborers and mechanics to do necessary work in and about the construction and repair of the tipple and top works at the coal mine. Robertson also employed miners to dig coal. On November 29 or 30, 1906, the lessor, Miller, declared a forfeiture of the lease for non-payment of rent and took possession of the premises. Thereafter appellees filed their bill in equity against Miller and Robertson to establish and enforce a mechanic\u2019s lien upon the premises for work performed and material furnished by them in repairing and constructing said tipple and top works at the mine, and for labor performed in mining coal therein. On the hearing before the chancellor upon the evidence taken and reported by the master in chancery, a decree was entered finding that the several petitioners were entitled to a mechanic\u2019s lien upon the premises involved for the several amounts due said petitioners, aggregating the sum of $304.53, together with the sum of $60 as their reasonable solicitor\u2019s fees to be taxed as costs. To reverse this decree Samuel M. Miller appeals to this court.\nAppellees predicate their right to the enforcement of a lien in said case upon the provisions of section 1 of the Mechanic\u2019s Lien Act of this state. Hurd\u2019s Stat. 1905, 1317. The evidence tends to show that the top works and tipple at the mine in question, at the time Robertson took possession under his lease from appellant, were dilapidated and out of repair, and that it was necessary to construct and repair the same to properly operate the mine. The evidence further tends to show that appellant was present while the work of construction and repair was being performed and that he made no objection thereto. The conduct of appellant in this regard taken in connection with the provisions of the lease, which authorized the making of improvements by the lessee, which improvements were to become the property of the lessor at the expiration of the term, entitles appellees to a lien therefor within the terms of the statute, which provides that, the person furnishing material or performing labor under contract with the owner, \u201cor with one whom such owner has authorized or knowingly permitted to contract for the improvements,\u201d shall have a lien, etc.\nIn so far as the several amounts awarded to appellees include pay for their labor in mining coal the decree cannot be sustained. The labor performed in mining coal in the regular course of operating the mine was not performed in the making of any improvement within the meaning of the statute providing for a lien. The allowance of solicitor\u2019s fees to be taxed as costs was also erroneous. Manowsky v. Stephan, 233 Ill. 409.\nThe decree of the Circuit Court awarding a lien to appellees for labor performed and material furnished in constructing and repairing the top works and tipple at the mine will be affirmed, and such decree will be reversed wherein it awards to appellees a lien for labor performed in mining coal, and wherein it provides for the payment of solicitor\u2019s fees by appellant. One half of the costs herein will be taxed against appellant and one-half against the appellees.\nDecree affirmed in part and reversed in part and ' the cause remanded for further proceedings not inconsistent with the views here expressed.\nAffirmed in part, reversed in part and remanded.",
        "type": "majority",
        "author": "Mr. Justice Baume"
      }
    ],
    "attorneys": [
      "Jett & Kinder, for appellant.",
      "Lane & Cooper, for appellees."
    ],
    "corrections": "",
    "head_matter": "Joseph Henry et al., Appellees, v. Samuel M. Miller, Appellant.\n1. Mechanic\u2019s liens\u2014when owner liable for repairs made by lessee. A lien will be enforced against the owner of land for repairs made by his lessee where the lease provided that the lessee shall make such improvements and that the same shall become the property of the lessor at the expiration of the lease.\n2. Mechanic\u2019s liens\u2014what not subject of. Labor performed in mining coal in the regular course of operating a mine is not performed in the making of any improvement within the meaning of the statute providing for mechanic\u2019s liens and therefore cannot be made the basis of mechanic\u2019s lien relief.\n3. Mechanic\u2019s liens\u2014allowance of solicitor's fees improper. The mechanic\u2019s lien statute which provides for the allowance of solicitor\u2019s fees to the plaintiff\u2019s solicitor, is unconstitutional and such an allowance is improper.\nBill in equity. Appeal from the Circuit Court of Montgomery county; the Hon. Samuel L. Dwight, Judge, presiding. Heard in this court at the May term, 1908.\nAffirmed in part and reversed in part and remanded.\nOpinion filed November 17, 1908.\nJett & Kinder, for appellant.\nLane & Cooper, for appellees."
  },