{
  "id": 3221910,
  "name": "Hegeman-Harris Company, Inc., Appellant, v. Tebbetts and Garland Company, Appellee",
  "name_abbreviation": "Hegeman-Harris Co. v. Tebbetts & Garland Co.",
  "decision_date": "1931-10-09",
  "docket_number": "Gen. No. 34,903",
  "first_page": "524",
  "last_page": "537",
  "citations": [
    {
      "type": "official",
      "cite": "262 Ill. App. 524"
    }
  ],
  "court": {
    "name_abbreviation": "Ill. App. Ct.",
    "id": 8837,
    "name": "Illinois Appellate Court"
  },
  "jurisdiction": {
    "id": 29,
    "name_long": "Illinois",
    "name": "Ill."
  },
  "cites_to": [
    {
      "cite": "181 Ill. App. 212",
      "category": "reporters:state",
      "reporter": "Ill. App.",
      "case_ids": [
        880163
      ],
      "pin_cites": [
        {
          "page": "214"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ill-app/181/0212-01"
      ]
    },
    {
      "cite": "169 Ill. App. 589",
      "category": "reporters:state",
      "reporter": "Ill. App.",
      "case_ids": [
        2787087
      ],
      "pin_cites": [
        {
          "page": "592"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ill-app/169/0589-01"
      ]
    },
    {
      "cite": "223 Ill. 88",
      "category": "reporters:state",
      "reporter": "Ill.",
      "case_ids": [
        3336010
      ],
      "pin_cites": [
        {
          "page": "93"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ill/223/0088-01"
      ]
    },
    {
      "cite": "274 Ill. 369",
      "category": "reporters:state",
      "reporter": "Ill.",
      "case_ids": [
        2407428
      ],
      "pin_cites": [
        {
          "page": "378"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/ill/274/0369-01"
      ]
    },
    {
      "cite": "264 Fed. 66",
      "category": "reporters:federal",
      "reporter": "F.",
      "case_ids": [
        6730053
      ],
      "pin_cites": [
        {
          "page": "69"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/f/264/0066-01"
      ]
    },
    {
      "cite": "145 N. Y. S. 201",
      "category": "reporters:state",
      "reporter": "N.Y.S.",
      "case_ids": [
        3284767
      ],
      "pin_cites": [
        {
          "page": "202"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/nys/145/0201-01"
      ]
    }
  ],
  "analysis": {
    "cardinality": 780,
    "char_count": 24057,
    "ocr_confidence": 0.517,
    "pagerank": {
      "raw": 5.527646540942415e-08,
      "percentile": 0.34501992201089715
    },
    "sha256": "1dd58a01071dbad0450092b162dc0e5118b521a5f39e2be6d0935078aa5ddaba",
    "simhash": "1:ab73bbed0281c8be",
    "word_count": 3924
  },
  "last_updated": "2023-07-14T18:50:04.606085+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "Hegeman-Harris Company, Inc., Appellant, v. Tebbetts and Garland Company, Appellee."
    ],
    "opinions": [
      {
        "text": "Mr. Presiding Justice Gridley\ndelivered the opinion of the court.\nIn an action in assumpsit, commenced on April 22, 1930, and based upon a building contract, plaintiff (contractor) sought to recover of defendant (owner) the sum of $17,024.88. The cause was tried before the court without a jury and on November 18, 1930, the court found the issues in favor of defendant and entered a judgment against plaintiff for costs. The present appeal followed.\nPlaintiff\u2019s declaration consists of two special counts and the common counts. In the first special count the contract, dated March 17, 1928, is set forth in full. It is signed.by defendant, as first party and designated as the \u201cOwner\u201d and by plaintiff, as second party ahd designated as the \u201cGeneral Contractor.\u201d It recites that on December 14, 1927, the parties entered into another contract by the terms of which the contractor was to commence the erection of a building at Nos. 16-30 West Washington street, Chicago; that it commenced the work; that complete plans and specifications have been drawn by Schmidt, Garden and Erik-son, architects; that in pursuance of the work already, done various contracts have been let for parts of the work by the contractor \u201cin the name of and as the agent of the owner \u2019 \u2019; and that it has been determined to make a contract between the parties by which the contractor \u201cshall become the General Contractor for the erection and construction of said building, according to said complete plans and specifications.\u201d Then follow 24 paragraphs, some of which are in substance as follows:\nParagraph 1. The General Contractor (plaintiff) is to furnish all labor, materials, etc. necessary for the erection and completion of the store and office building on the premises, as called for by the complete plans and specifications and under the directions of the architects.\nPar. 3. The Owner (defendant) is to pay to the General Contractor \u201cthe actual cost of said erection and completion plus a fixed fee to the General Contractor of five per cent (5%) on said actual cost\u201d (except on the cost of the steel delivered on which the 'fixed fee is to be 2%) subject to the following qualifications, terms and conditions:\n\u201cThe General Contractor hereby guarantees to the Owner that the cost of the erection and completion of said building (including the cost of all work heretofore contracted for and/or completed or partially completed by the General Contractor under said contract of December 14, 1927), including the fixed fee of said General Contractor, will not exceed the sum of $2,254,418, which, sum is hereinafter referred to as the \u2018Maximum Guaranteed Cost,\u2019 and if the actual cost of said building, as above defined, inclusive of the fixed fee of the General Contractor, exceeds said Maximum Guaranteed Cost, then the General Contractor agrees to pay from its own funds all amounts in excess of said Maximum Guaranteed Cost.\u201d (Then follows the statement that in said Maximum Guaranteed Cost no provision has been made for seven mentioned items entering into said construction. Two of these items are (4) \u201cthe cost of bonds, if any, furnished by subcontractors,\u201d excepting one mentioned bond already given, and (7) \u201cthe amount by which any subcontract let at the direction of the Owner shall exceed the amount of any bid for the same work received by the General Contractor from a subcontractor, who shall be approved by the Architects and whom the Owner directs the General Contractor not to contract with\u201d). . . .\n\u201cIn no event however shall the Owner be required to pay to the General Contractor a greater amount than the actual cost of the erection and completion of said building according to said complete plans and specifications, plus said fixed fee of said General Contractor, as aforesaid.\u201d\nPar. 4. \u201cThe General Contractor may with the written approval of the Architects and the Owner, sublet all or any portion of the work required to be done hereunder.\u201d . . . \u201cThe question of requiring surety bonds from the subcontractors, or any of them, shall be determined by the General Contractor.\u201d\n\u201cThe General Contractor shall, however, and does hereby, assume full responsibility for the performance by the subcontractors, in the manner and under the conditions provided and required under the complete plans and specifications and the terms of this agreement, of the work called for by such subcontracts, and full responsibility for the performance of all work remaining unfinished under any and all contracts heretofore let by the General Contractor in the name of and as agent of the Owner\u201d (subject to certain qualifications mentioned in succeeding paragraphs.)\nPar. 10. The General Contractor is to submit monthly requisition statements to the Owner and Architects, showing all work done by it and the cost thereof, and also all work done and/or materials furnished by any subcontractor together with the amount due therefor. \u2018\u2018Architects\u2019 certificates shall be issued within ten (10) days after such requisition statement is made therefor for the amounts as determined by the Architects to be due the General Contractor for the work done by said General Contractor, including the proportionate \u00e1mount of the fixed fee then due to the General Contractor and for 85 per cent of the amount due any and all subcontractors. \u2019 \u2019\nPar. 11. After the work of any subcontractor has been completed and a sufficient time has elapsed to demonstrate that such work has been properly done, etc., \u201call or any part of said 15 per cent reserved from the amount due any subcontractor shall, upon architects\u2019 certificates be paid to the General Contractor for such subcontractor.\u201d\nPar. 13. \u201cAll moneys at any time paid hereunder to the General Contractor shall be deposited by it in a special bank account-in the Bank of America, in which no other funds are to be deposited except the special trust fund of $10,000, hereinafter provided for. The moneys in such special bank account at any time are to be applied and disbursed prior to the final completion and payment in full for said improvements only as follows :\n1. To the payment of the amount due the General Contractor, as shown by the 'Architects\u2019 certificates issued to it.\n2. To the payment of the amount due the subcontractors, material men and others as directed by Architects\u2019 certificates theretofore issued.\u201d . . .\nPar. 20. \u20181 The Owner reserves the right to require the General Contractor to employ a subcontractor designated by the Owner and approved by the Architects on any part of the work which is to be sublet; and to require the General Contractor to take bids on any part of the work which the General Contractor itself proposes to do, . . .\u201d\nIn said first special count it is alleged that \u201cplaintiff has done all things necessary for the construction and completion of the building as required under said contract\u201d; that the building \u201cwas substantially completed and accepted by the Owner (defendant) more than one year prior to the date of the institution of this suit and has ever since been occupied and used by it and its tenants\u201d; that the total \u201cactual cost\u201d for the construction and completion of the building, \u201cexclu sive of the cost of extras and additions. . . was $2,035,562.20\u201d; that all of said amount, together with the contractor\u2019s fee thereon, has been paid by defendant, except the sum of $17,024.88 (including plaintiff\u2019s fee as contractor); that said last mentioned sum \u201cis the balance of the cost of painting, decorating and wood finishing on said building as provided in the plans and specifications\u201d; and that, although said sum is justly due and owing to plaintiff, defendant has refused upon request to pay the same to plaintiff, etc.\nIn the second special count similar allegations are made and it is also alleged that \u201cthe actual cost of additions and extras under the contract, . . . less deductions, was $253,132.56, which amount has been paid by defendant\u201d; that the \u201cmaximum guaranteed cost of $2,254,418,\u201d as provided in the contract, \u201cwas increased by said net amount of additions and extras of $253,132.56, making the maximum guaranteed cost, as adjusted, $2,507,550.56\u201d; that \u201cthe total actual cost to the general contractor (plaintiff) for the entire work included under the contract, with said net amount of additions and extras, was $2,288,694.76, and the contractor\u2019s fee . . . was $105,964.42, making a total of $2,394,659.18\u201d-; that all of said last mentioned sum has been paid by defendant except the sum of $17,024.88 (including plaintiff\u2019s fee as contractor); and that defendant, although often requested, has refused to pay to plaintiff said sum of $17,024.88, etc.\nTo the declaration defendant filed a plea of the general issue, and also an affidavit of merits in which it denied that the sum of $17,024,88, or any sum, was due to plaintiff. Prior to the trial defendant was allowed to file an amendment to its affidavit of merits in which it alleged, as an additional defense, the following:\n' \u2018 \u2018 That, pursuant to the terms and conditions of said contract, all payments to be made by defendant to plaintiff were to be made only as shown by architects \u2019 certificates, issued by the architects named therein (Schmidt, Garden & Erikson) to plaintiff and upon the presentation of such certificates to defendant; and that plaintiff has never received from said architects a certificate for the whole or any part of said sum of $17,024.88, sued for by plaintiff herein, and has never presented an architect\u2019s certificate therefor, or for any part thereof, to defendant. \u2019 \u2019\nDuring the trial, in addition to the testimony of witnesses presented by the parties and to certain documentary evidence introduced by plaintiff, including said contract of March 17, 1928, various stipulations or agreements were entered into, one of which is as follows :\n\u201cIt was agreed by counsel that the amount of overrun on painting was $16,214.17, for labor and materials, plus $810.71, for the contractor\u2019s fee of five per cent, or a total of $17,024.88. It was also agreed that the work was done and the material furnished and had been checked by the architect and found to be actually furnished, and that the total amount in contest in this action, and for which plaintiff sues, is $14,408.41, for the work done by Plamondon-Gabriel and materials furnished. It was also agreed by counsel that Hegeman-Harris Co. (plaintiff) had no subcontract with Plamondon-Gabriel but employed them, and they did the work on a time and material basis, which was paid for by Hegeman-Harris Co.\u201d\nAnd it was further stipulated and agreed as follows:\n\u201cThat after the default by the Sullivan Co. (subcontractor for the painting, etc.) and after Mr. Evans and Mr. Greenspahn (attorneys) were called into the matter, representing respectively the plaintiff and the defendant, Mr. Greenspahn took the position that under the contract it was the obligation of the contractor (plaintiff) to complete the painting job even though it cost more than the Sullivan contract, and Mr. Evans took the contrary position that it was the obligation of the owner (defendant), and those positions were maintained respectively by the representatives of the plaintiff and the defendant np to the time this suit was brought; and that it was further understood this Work should go ahead and the matter of the construction of the contract should be determined later.\u201d\nDuring the trial, also, plaintiff introduced two letters addressed to it and signed by defendant, by H. A. Loeb, Treas. One letter, dated January 2, 1930, is in part as follows:\n\u201cOn your alleged claim for the excess cost of the painting, which the architects and ourselves have refused to approve, allow or pay, amounting to $17,024.88, . . . it is understood that you have not released this claim in final settlement, and that you are free to pursue such course as you may determine to collect on this claim.\u201d\nThe other letter, dated January 13, 1930, is in part as follows:\n\u201cThis is to acknowledge receipt of your letter of January 8,1930, reading as follows: \u2018This is to certi'fy that the undersigned general contractor for the erection of the building at 16-30 West Washington street, Chicago, has completed said building in accordance with the plans and specifications therefor, and that the only outstanding claim in connection with the construction of the building under the contract with the undersigned is the claim of Ralph0 A. Bond & Co. for $2,129.11.\u2019\n\u201cWe acknowledge that the above letter was given by you in order that we might make an adjustment with the Trust Company who is holding funds on this job and is without prejudice to your claim for $17,024.88, being the excess cost of the painting, . . .\n\u201cAs to the item of excess cost of painting above specified, it is understood that you have not released this claim in any way, and are free to pursue such course as you may determine to collect on the same. \u2019 \u2019\nIt further appears from the evidence that plaintiff, with the. approval of the architects and defendant, made in all about fifty-two (52) subcontracts for work on the building; that of these subcontractors plaintiff saw fit to require performance bonds of only four or five of them; that one of the subcontracts was made with J. P. Sullivan Co. for the painting, etc. work, whose accepted bid was $17,880; that plaintiff did not require or obtain from it a performance bond; that the Sullivan Co. entered upon said painting etc. work and furnished labor and materials to the value of $7,647; that it was paid $6,500, or 85 per cent thereof; that it abandoned its contract and did no further work on the building; that afterwards plaintiff, with the approval of the architects and defendant, made an arrangement with Plamondon-Grabriel Co., upon a time and material basis, to complete said painting etc. work and the same thereafter was completed to the satisfaction of the architects; that the amount of the Sullivan contract, \u201cas adjusted by extras and additions,\u201d was $17,083.82, which sum was paid to plaintiff; and that.plaintiff, in causing the painting etc. work to be completed through Plamondon-Grabriel Co., expended, in addition to the Sullivan contract prices as adjusted, the said sum of $14,408.41, as stipulated.\nIt further appears from the terms of the contract sued upon and from other stipulations and agreements made on the trial.as follows:\nMaximum guaranteed cost as per contract $2,254,418.00\nStipulated extras to be added thereto .... 253,132.56\nMaximum guaranteed cost including said extras .............................$2,507,550.56\nTotal actual cost of building, including architects\u2019.fees, but excluding said sum of $14,408.41, in dispute for said painting work, as stipulated...............$2,377,634.30\nExcess of maximum cost, as guaranteed, over total actual cost......\u2022.......... $129,916.26\nIt thus appears that, if said sum of $14,408.41 should be allowed to plaintiff and paid by defendant, the total actual cost of the building to defendant would be less than said maximum guaranteed cost by about $115,500.\nIn urging that the finding and judgment of the trial court in defendant\u2019s favor should be affirmed, defendant\u2019s counsel make the following statements in their printed brief here filed:\n\u201cObviously, the Sullivan Co. did not perform the work called for by its subcontract. By the provisions of paragraph 4 of the contract (referred to above) plaintiff assumed full responsibility for the performance by the Sullivan Co. of the work called for by its subcontract. In other words, it guaranteed that the Sullivan Co. would do the work which its contract obligated it to do in accordance with the plans and specifications. Had the Sullivan- Co. completed \u2018the work called for by such subcontract\u2019 there would have been no additional cost to either plaintiff or defendant, for the Sullivan Co.\u2019s compensation was fixed. By reason of the Sullivan Co.\u2019s default the work called for by its subcontract cost an additional $14,408.41. Who should pay this additional cost? That is the law suit.\n\u201cDefendant contends that, unless the language of paragraph 4 of the contract is to be robbed of all significance, the agreement of Hegeman-Harris Co., to assume full responsibility for the performance by Sullivan Co. of the work called for by its subcontract, amounts to a guaranty of performance: Sullivan Co. \u2019s failure to perform the work which it contracted to do was the sole cause of the additional expenditures made necessary in order to finish the Sullivan subcontract. Therefore, as between plaintiff and defendant, plaintiff, who had contracted to see that subcontractors fully performed their subcontracts, should bear the additional expense.\u201d\nReplying to the above contentions, plaintiff\u2019s counsel contend that, although by the provisions of paragraph 4 of the contract plaintiff \u201cassumed full responsibility for the performance by the Sullivan Co. of the work called for by its subcontract,\u201d there is nothing in said paragraph 4, or in the entire contract, to sustain the claim that plaintiff guaranteed that the painting work on the building would be done at the price named in the Sullivan Co.\u2019s subcontract. And plaintiff\u2019s counsel further contend that the particular clause (relied upon by defendant\u2019s counsel), in said paragraph 4, was inserted \u201cnot as a guaranty of cost, but as one of various clauses to maintain the relation of owner and independent contractor as distinguished from the relation of principal and agent.\u201d\nAfter considering the entire contract, and particularly the provisions of paragraphs 3 and 4, we agree with said contentions of plaintiff\u2019s counsel. We do not find anywhere in the contract that plaintiff guaranteed that the work to be performed by any subcontractor should be performed at the price named in the subcontract. We do find, however, that in paragraph 3 the general contractor (plaintiff) guaranteed to the owner (defendant) that the cost of the entire work on the building, including the fixed fee of said contractor, should not exceed a certain named sum, which is termed the \u201cMaximum Guaranteed Cost.\u201d And in said paragraph 3 there is the further provision that \u201cif the actual cost of said building, . . . inclusive of the fixed fee of the general contractor, exceeds said Maximum Guaranteed Cost, then the general contractor agrees to pay from its own funds all amounts in excess of said Maximum Guaranteed Cost.\u201d And it appears from the stipulated facts and the evidence that if said sum of $14,408.41 (here involved) be paid to plaintiff by defendant, said Maximum Guaranteed Cost will not be exceeded. Furthermore, we are of the opinion that, if the construction as to paragraph 4 of the contract, as urged by defendant\u2019s counsel, is to be adopted, the practical effect is to nullify the provisions of paragraph 3 as to the Maximum Guaranteed Cost of the entire work. It appears from the evidence that there were about 52 subcontracts let for the work on the building and that the aggregate amount of these contracts (exclusive of the \u201coverrun\u201d on the Sullivan Co.\u2019s painting contract) was in excess of $2,150,000. We do not think that under all the provisions of the contract it was the intention of the parties that the general contractor, in addition to guaranteeing that the Maximum Cost of the entire work should not exceed a certain named sum, should also guarantee the performance of 52 separate subcontracts at the respective prices named therein. Such a construction of a \u201ccost plus\u201d contract, as is the present contract, would not in our opinion be fair to the contractor, and the tendency of the courts is to construe such contracts liberally. (Westinghouse, Church, Kerr & Co. v. Long Island R. Co., 145 N. Y. S. 201, 202; Standard Oil Co. v. United States, 264 Fed. 66, 69; see, also, R. F. Conway Co. v. City of Chicago, 274 Ill. 369, 378.)\nDefendant\u2019s counsel call attention to a clause in paragraph 4 of the contract where, as they state, the general contractor (plaintiff) is given the right at its discretion to require performance bonds from all subcontractors, and they contend that said clause \u201cclearly indicates the intention of the parties to make the general contractor liable for performance by subcontractors, and at the same time to enable the general contractor to be fully protected against loss by reason of its guaranty.\u201d We fail to see wherein this particular clause has any material bearing on the present issue. Plaintiff was not at fault in failing to require a performance bond from the Sullivan Co. Whether or not a subcontractor\u2019s bond should be required of any subcontractor was, under the wording of said clause, solely within the discretion of the general contractor (plaintiff). And the evidence shows that it required performance bonds from only four or five of the 52 subcontractors.\nDefendant\u2019s counsel further contend in substance that, even if the trial court was wrong in construing the contract as placing an obligation upon plaintiff of seeing to it that subcontractors perform the work called for by these subcontracts and at the prices named therein, nevertheless the judgment appealed from was right, for the reason that it was made a condition precedent in the contract that, before plaintiff could recover for the amount here involved ($14,408.41), it must obtain an architect\u2019s certificate therefor and no such certificate was issued, although requested. After considering the provisions as contained in paragraphs 10,11 and 13 (above mentioned) of the contract, wherein architects\u2019 certificates are referred to, we do not think that, because of the provisions in said paragraphs or of any other provisions in the contract, it should be held that the obtaining by plaintiff of an architect\u2019s certificate was a condition precedent to the payment to it of the particular sum which it now seeks. Furthermore, in view of defendant\u2019s letters to plaintiff of January 2, and January 13, 1930 (above set forth), of .the stipulations made upon the trial, and of certain undisputed testimony of plaintiff\u2019s witnesses, Hall and Baxendale, we are of the opinion that, even if the obtaining of an architects\u2019 certificate might be considered as a condition precedent to the payment of said particular sum, the condition should be held to have been waived by defendant. In Andrew Lohr Bottling Co. v. Ferguson, 223 Ill. 88, 93 (a building contract case), it is said:\u20181 There can be no doubt of the rule that a party having a right to insist upon a condition precedent to the payment of money or other performance on his part will waive the condition precedent by a total denial of liability or by placing his refusal to perform on other grounds. This rule has often been applied to contracts of insurance, but it is a salutary and well established rule of the common law, the application of which to all contracts will effect justice and cut off subsequently discovered excuses for the violation of contract engagements.\u201d (See, also, Masek v. Chmelik, 169 Ill. App. 589, 592; Connelly v. Wallin, 181 Ill. App. 212, 214.)\nOur conclusions are that the superior court erred in entering the judgment appealed from in favor of defendant, and that, under the undisputed and stipulated facts, plaintiff is entitled to recover of defendant the sum of $14,408.41, as a matter of law. Accordingly the judgment of the superior court is reversed, and judgment will be entered here in favor of HegemanHarris Co., Inc. (plaintiff), and against Tebbetts and Garland Company (defendant), in the sum of $14,408.41, together with costs in this and the superior court.\nReversed, and judgment here against defendant.\nKeener and Scanean, JJ., concur.",
        "type": "majority",
        "author": "Mr. Presiding Justice Gridley"
      }
    ],
    "attorneys": [
      "Taylor, Miller, Busch & Boyden and Evans & Robinson, for appellant; Eidlitz & Hulse, of counsel.",
      "Poppenhusen, Johnston, Thompson & Cole, for appellee ; Edward R. Johnston and Edward J. Fleming, of counsel."
    ],
    "corrections": "",
    "head_matter": "Hegeman-Harris Company, Inc., Appellant, v. Tebbetts and Garland Company, Appellee.\nGen. No. 34,903.\nOpinion filed October 9, 1931.\nRehearing denied October 21, 1931.\nTaylor, Miller, Busch & Boyden and Evans & Robinson, for appellant; Eidlitz & Hulse, of counsel.\nPoppenhusen, Johnston, Thompson & Cole, for appellee ; Edward R. Johnston and Edward J. Fleming, of counsel."
  },
  "file_name": "0524-01",
  "first_page_order": 556,
  "last_page_order": 569
}
