  "id": 8521669,
  "name": "STATE OF NORTH CAROLINA ex rel. UTILITIES COMMISSION; PUBLIC STAFF-NORTH CAROLINA UTILITIES COMMISSION; LACY H. THORNBURG, Attorney General; CAROLINA POWER & LIGHT COMPANY; DUKE POWER COMPANY; NANTAHALA POWER AND LIGHT COMPANY; NORTH CAROLINA CUSTOMERS ASSOCIATION, INC.; CAROLINA INDUSTRIAL GROUP FOR FAIR UTILITY RATES (CIGFUR-II); CONSERVATION COUNCIL OF NORTH CAROLINA; NORTH CAROLINA FAIR SHARE; NORTH CAROLINA CONSUMERS COUNCIL; NORTH CAROLINA SOLAR ENERGY ASSOCIATION; WESTERN NORTH CAROLINA ALLIANCE; SIERRA CLUB; JOCASSEE WATERSHED COALITION; ULTRASYSTEMS DEVELOPMENT CORPORATION; BLUE RIDGE ENVIRONMENTAL DEFENSE LEAGUE, INC.; and DAVID SPRINGER, Appellees v. NORTH CAROLINA ELECTRIC MEMBERSHIP CORPORATION, Appellant",
  "name_abbreviation": "State ex rel. Utilities Commission v. North Carolina Electric Membership Corp.",
  "decision_date": "1992-01-21",
  "docket_number": "No. 9010UC1166",
  "first_page": "136",
  "last_page": "146",
  "citations": [
    {
      "type": "official",
      "cite": "105 N.C. App. 136"
    }
  ],
  "court": {
    "name_abbreviation": "N.C. Ct. App.",
    "id": 14983,
    "name": "North Carolina Court of Appeals"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [
    {
      "cite": "N.C. Gen. Stat. \u00a7 62-73",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "year": 1989,
      "opinion_index": 0
    },
    {
      "cite": "37 L.Ed.2d 405",
      "category": "reporters:federal",
      "reporter": "L. Ed. 2d",
      "year": 1973,
      "opinion_index": 0
    },
    {
      "cite": "412 U.S. 944",
      "category": "reporters:federal",
      "reporter": "U.S.",
      "case_ids": [
        6265777,
        6265163,
        6265419,
        6266427
      ],
      "year": 1973,
      "opinion_index": 0,
      "case_paths": [
        "/us/412/0944-03",
        "/us/412/0944-01",
        "/us/412/0944-02",
        "/us/412/0944-04"
      ]
    },
    {
      "cite": "411 U.S. 747",
      "category": "reporters:federal",
      "reporter": "U.S.",
      "case_ids": [
        10104
      ],
      "weight": 2,
      "year": 1973,
      "opinion_index": 0,
      "case_paths": [
        "/us/411/0747-01"
      ]
    },
    {
      "cite": "426 U.S. 271",
      "category": "reporters:federal",
      "reporter": "U.S.",
      "case_ids": [
        6175834
      ],
      "weight": 2,
      "year": 1976,
      "opinion_index": 0,
      "case_paths": [
        "/us/426/0271-01"
      ]
    },
    {
      "cite": "476 U.S. 953",
      "category": "reporters:federal",
      "reporter": "U.S.",
      "case_ids": [
        12862
      ],
      "weight": 2,
      "year": 1986,
      "opinion_index": 0,
      "case_paths": [
        "/us/476/0953-01"
      ]
    },
    {
      "cite": "N.C. Gen. Stat. \u00a7 62-110.1",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "pin_cites": [
        {
          "page": "(c)"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "N.C. Gen. Stat. \u00a7 62-2",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "year": 1989,
      "pin_cites": [
        {
          "page": "(3a)"
        }
      ],
      "opinion_index": 0
    }
  ],
  "analysis": {
    "cardinality": 976,
    "char_count": 25323,
    "ocr_confidence": 0.778,
    "pagerank": {
      "raw": 4.03580807328026e-08,
      "percentile": 0.2054990464695046
    },
    "sha256": "69119c73eb731d899020158b5441be512056e76ac97c512cfa3fc6568ac5a7b5",
    "simhash": "1:afe06939d2dfaed0",
    "word_count": 3961
  },
  "last_updated": "2023-07-14T19:24:40.355340+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [
      "Judges COZORT and ORR concur."
    ],
    "parties": [
      "STATE OF NORTH CAROLINA ex rel. UTILITIES COMMISSION; PUBLIC STAFF-NORTH CAROLINA UTILITIES COMMISSION; LACY H. THORNBURG, Attorney General; CAROLINA POWER & LIGHT COMPANY; DUKE POWER COMPANY; NANTAHALA POWER AND LIGHT COMPANY; NORTH CAROLINA CUSTOMERS ASSOCIATION, INC.; CAROLINA INDUSTRIAL GROUP FOR FAIR UTILITY RATES (CIGFUR-II); CONSERVATION COUNCIL OF NORTH CAROLINA; NORTH CAROLINA FAIR SHARE; NORTH CAROLINA CONSUMERS COUNCIL; NORTH CAROLINA SOLAR ENERGY ASSOCIATION; WESTERN NORTH CAROLINA ALLIANCE; SIERRA CLUB; JOCASSEE WATERSHED COALITION; ULTRASYSTEMS DEVELOPMENT CORPORATION; BLUE RIDGE ENVIRONMENTAL DEFENSE LEAGUE, INC.; and DAVID SPRINGER, Appellees v. NORTH CAROLINA ELECTRIC MEMBERSHIP CORPORATION, Appellant"
    ],
    "opinions": [
      {
        "text": "WYNN, Judge.\nIn 1975, the North Carolina General Assembly enacted G.S. 62-110.1(c) (1989), which directed the North Carolina Utilities Commission (the \u201cCommission\u201d) to \u201cdevelop, publicize, and keep current an analysis of the long-range needs for expansion of facilities for the generation of electricity in North Carolina, including its estimate of the probable future growth of the use of electricity, the probable needed generating reserves, the extent, size, mix and general location of generating plants and arrangements for pooling power . . . .\u201d 1975 N.C. Sess. Laws ch. 780, \u00a7 1. In the course of making this analysis and developing a plan, the Commission must confer and consult with the public utilities in North Carolina, conduct public hearings, and ultimately submit a report of its analysis and plan to the Governor and to appropriate committees of the General Assembly.\nThe parties are in general agreement that prior to 1987, the Commission\u2019s and the utilities\u2019 general practice was to focus strictly on \u201csupply-side\u201d considerations in analyzing the long-range needs for electricity in North Carolina. Supply-side considerations relate to increasing the supply of power available to a given utility, either by building new electricity generating units or by purchasing power from other utilities. In June 1987, however, the General Assembly enacted legislation amending N.C. Gen. Stat. 62-2 (The Public Utilities Act\u2019s \u201cDeclaration of Policy\u201d) by adding a new subsection (3a). See 1987 N.C. Sess. Laws, ch. 354, \u00a7 1. The policy of the State of North Carolina follows:\nTo assure that resources necessary to meet future growth through the provision of adequate, reliable utility service include use of the entire spectrum of demand-side options, including but not limited to conservation, load management and efficiency programs, as additional sources of energy supply and/or energy demand reductions. To that end, to require energy planning and fixing of rates in a manner to result in the least cost mix of generation and demand-reduction measures which is achievable, including consideration of appropriate rewards to utilities for efficiency and conservation which decrease utility bills.\nN.C. Gen. Stat. \u00a7 62-2(3a) (1989).\nThe parties are also in general agreement that the practical effect of. adding subsection (3a) to G.S. 62-2 was to codify both the Commission\u2019s and the utilities\u2019 growing tendency to take \u201cdemand-side\u201d considerations into account when complying with the directives of section 62-110.1(c). Demand-side considerations focus on the consumer\u2019s need for electricity, as well as ways to reduce that need. In response to the newly-enacted section 62-2(3a) and following several months of meetings and discussions, the Commission issued an Order on 8 December 1988 adopting Commission Rules R8-56 through R8-61 which set forth the process by which the Commission would comply with the new mandate. This process is known as \u201cleast cost integrated resource planning.\u201d\nAlso on 8 December 1988, the Commission issued an Order stating the following: \u201cIntegrated resource planning is a strategy which considers conservation, load management and other demand-side programs along with new generating plants, cogeneration and other supply-side options in providing cost-effective, high quality electric service.\u201d The Order required the utility companies subject to its Rules to file their least-cost integrated resource plans (\u201cLCIRPs\u201d) with the Commission, and scheduled hearings in six different cities to analyze and investigate each utility\u2019s plan. Each plan filed was required to contain energy and peak load forecasts for at least fifteen years; an integrated resource plan giving due consideration to existing and new generating facilities, alternative energy resources, conservation and load management programs, purchased power, and transmission and distribution facilities; and a short-term action plan. Appellees Duke Power Company (\u201cDuke\u201d) and Carolina Power and Light (\u201cCP&L\u201d) were among the electric utility companies which filed LCIRPs with the Commission.\nPursuant to the Commission\u2019s invitation to all interested parties, the North Carolina Electric Membership Corporation (\u201cNCEMC\u201d) petitioned to intervene and be heard during the hearings. NCEMC is comprised of twenty-seven electric distribution cooperatives which provide retail electric service to many areas of North Carolina. It also co-owns the Catawba Nuclear Station with Duke Power Company and the Saluda River Electric Cooperative. In its motion, NCEMC alleged that the \u201c[identification and utilization of least cost resource planning [was] critical to [its] successful operation.\u201d By Order dated 25 September 1989, NCEMC was allowed to intervene. Thereafter, NCEMC filed the testimony of three witnesses for the Commission\u2019s consideration.\nOn 12 December 1989, appellees Duke and CP&L filed separate motions to strike the testimony of each of the witnesses proffered by NCEMC. After considering the motions, the Commission decided to defer its consideration of two of the three witnesses\u2019 testimony until a later time. Thereafter, the matter came on for hearing on 9 January 1990. Following the hearing, the Commission issued an Order on 17 May 1990, stating the following finding of fact: \u201c7. The Least Cost Integrated Resource Plans (LCIRP) filed by CP&L, Duke, and North Carolina Power are reasonable for the purposes of this proceeding. The Commission recognizes that LCIRP is an evolving, dynamic process, and that new information and new understanding of resource planning principles will be developed in the near future. The LCIRPs filed herein are at an early stage in their evolution, and these plans should be recognized as a good faith attempt to achieve an appropriate generation mix at least cost consistent with reliable service.\u201d NCEMC now appeals the Commission\u2019s 17 May 1990 final order.\n\u25a0 I.\nIn its first assignment of error, NCEMC contends that the Commission erred in granting its \u201cunqualified approval\u201d of the LCRIPs submitted by Duke and CP&L. In this regard, NCEMC asserts that since the Commission deferred consideration of the testimony of two of NCEMC\u2019s witnesses, the substance of which NCEMC contends tended to show that the plans filed by Duke and CP&L were not least-cost, the better course of action for the Commission would have been to either reserve its judgment or, at most, lend its \u201cconditional approval\u201d of the Duke and CP&L plans.\nAlthough NCEMC assigns error only to the Commission\u2019s entry of an \u201cunconditional\u201d final order and not to its decision to defer consideration of the testimony, it nonetheless would be helpful to an understanding of NCEMC\u2019s position to set forth the substance of those witnesses\u2019 testimony.\nAt the hearing, NCEMC presented to the Commission deposition-like testimony elicited from Dr. Richard Bower, an economist and former member of the New York Public Service Commission, and Anis Sherali, a power supply engineer.\nDr. Bower\u2019s testimony focused on one important aspect of CP&L\u2019s supply-side plan: CP&L\u2019s announced intention to purchase 400 MW of generating capacity from Duke between 1992 and 1997, under a contract referred to as the \u201cSchedule J\u201d transaction. Bower analyzed the economics of the Schedule J transaction and concluded that it did not make good economical sense. It was his testimony that CP&L could meet its generation needs more economically if it were to facilitate a program whereby NCEMC could transfer excess power being generated through NCEMC\u2019s Catawba Nuclear Station entitlement to CP&L. The rationale underlying Bower\u2019s testimony is that seventeen of NCEMC\u2019s member cooperatives are located in areas controlled by CP&L, and those cooperatives receive their power requirements from NCEMC, which in turn receives its power supply through wholesale contracts with CP&L; CP&L, therefore, could meet its increased need for generating capacity more economically through a transfer of NCEMC\u2019s excess power from Catawba to the CP&L area. CP&L has refused to agree to such a transfer. In sum, the Bower testimony was proffered to indicate that the CP&L and Duke plans were not \u201cleast-cost.\u201d\nSherali\u2019s testimony was similar to that elicited from Bower; however, Sherali used a different method of analysis. Sherali testified that even if NCEMC were not allowed to transfer generating capacity from Catawba, the Schedule J transaction nonetheless would impose unnecessary costs upon CP&L ratepayers.\nFor the reasons which follow, we are of the opinion that the Commission correctly handled these proceedings. First, the Commission did not, as NCEMC contends, grant \u201cunqualified approval\u201d of the Duke and CP&L LCIRPs; rather, the Commission found as fact in its 17 May 1990 order only that the Duke and CP&L plans were \u201creasonable for the purposes of [the] proceeding\u201d before it. That is to say, the plans submitted by Duke and CP&L were reasonable for the purpose of \u201canalysing] . . . the long-range needs for expansion of facilities for the generation of electricity in North Carolina . . . .\u201d See N.C. Gen. Stat. \u00a7 62-110.1(c). Moreover, in response to concerns expressed in a motion filed by the Utilities Commission Public Staff that the Commission\u2019s 17 May 1990 order might be construed as \u201cadopting\u201d Duke\u2019s, CP&L\u2019s and other companies\u2019 LCIRPs, the Commission expressly reiterated that the 17 May 1990 order merely found the power companies\u2019 LCIRPs reasonable for the purposes outlined in G.S. 62-110.1(c); the Commission also expressly made it clear that the LCIRP proceedings were not meant to serve as a substitute for certification proceedings pursuant to G.S. 62-110 or 62-110.1(a).\nSecond, in its pre-hearing order deferring consideration of Bower\u2019s and Sherali\u2019s testimony, the Commission stated that it would consider the testimony after the Federal Energy Regulatory Commission (\u201cFERC\u201d) had reached a decision in a case in which the testimony of both Bower and Sherali was used. In addition to their assertions that the Schedule J transaction did not promote a least-cost objective, Bower and Sherali also contended that the Schedule J transaction would tend to suppress competition between CP&L and NCEMC\u2019s member cooperatives, and that CP&L had entered into the transaction in bad faith and in violation of federal antitrust laws. Duke and CP&L based their motions to strike Bower\u2019s and Sherali\u2019s testimony on the ground that the same issues presented by their testimony in the instant case were before FERC in a proceeding which was already underway. We agree with the appellees that the testimony of Bower and Sherali raises issues which are more appropriately directed to the attention of the Federal Energy Regulatory Commission. The Federal Power Act, 16 U.S.C. \u00a7\u00a7 791a to 828c, authorizes FERC to regulate interstate wholesale electric power transactions. More importantly, FERC\u2019s authority over these transactions is exclusive and is not shared with state regulatory agencies. Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 90 L.Ed.2d 943 (1986). Under 16 U.S.C. \u00a7 824d, a utility may not enter into a wholesale power transaction unless FERC has approved the rates and found them to be just and reasonable. As such, Duke and CP&L have submitted the Schedule J transaction for the FERC\u2019s approval. Since one of the factors which FERC considers in determining what is just and reasonable is whether the proposed transaction will have anti-competitive effects or will violate antitrust laws, Federal Power Comm\u2019n v. Conway Corp., 426 U.S. 271, 48 L.Ed.2d 626 (1976); Gulf States Utilities Co. v. Federal Power Comm\u2019n, 411 U.S. 747, 36 L.Ed.2d 635, reh\u2019g denied, 412 U.S. 944, 37 L.Ed.2d 405 (1973), and since NCEMC was allowed to intervene and submit the Bower and Sherali testimony in the proceedings for FERC\u2019s approval of the Schedule J transaction, NCEMC\u2019s concerns about the Schedule J transaction are being addressed adequately and appropriately in the proceedings which are currently before FERC. Moreover, since the Commission has expressly left the Bower and Sherali testimony open for consideration, we must conclude that NCEMC has suffered no prejudice by virtue of the Commission\u2019s decision finding Duke\u2019s and CP&L\u2019s LCIRPs reasonable.\nII.\nNCEMC next contends that the Commission erred in refusing to order CP&L to supply NCEMC with CP&L\u2019s \u201creal-time\u201d demand signal. A \u201creal-time system signal\u201d is an electronic signal which, when used with the proper equipment, provides a continuous indication of the total demand on a given utility\u2019s system. Although it is unclear from the record, it is presumably those service areas in which NCEMC\u2019s member cooperatives are located, but which are controlled by CP&L, to which NCEMC wishes the signal to be sent. According to NCEMC, it is the real-time system demand signal which allows utilities like CP&L to implement one of the most effective demand-side management techniques: shutting down or curtailing certain categories of use (e.g. domestic hot water heaters) during periods of peak demand. NCEMC asserts that, in order for such a program to operate efficiently, a utility must have accurate information from moment to moment regarding the level of demand on its system, and that the real-time system demand signal provides this information. NCEMC argues that since CP&L refuses to provide NCEMC with its signal, NCEMC is forced to speculate as to the precise time and length of the periods of peak demand on CP&L\u2019s system and that, as a result, voluntary participation on the part of NCEMC\u2019s member cooperatives\u2019 retail customers in programs designed to disrupt service during peak periods of demand is discouraged because the cooperatives inevitably disrupt the service for periods which are longer than necessary. It is NCEMC\u2019s position that in declining to order CP&L to make its signal available to NCEMC, the Commission \u201cwas heedless of its statutory mandate to promote \u2018the least-cost mix of generation and demand-reduction measures which is achievable ....\u2019\u201d We disagree.\nAlthough the issue of CP&L\u2019s providing its real-time system demand signal to NCEMC arguably bears some relevance to the effectiveness of CP&L\u2019s LCIRP, this Court is of the opinion that the newly-designed least-cost integrated resource planning proceeding was not intended to provide an occasion for the issuance of mandatory orders requiring substantive changes in a given utility\u2019s operations.\nGeneral Statutes section 62-110.1(c) makes it clear that the only purpose of a least-cost planning proceeding is to assist the Utilities Commission in \u201cdeveloping], publicizing], and keeping] current an analysis of the long-range needs for expansion of facilities for the generation of electricity in North Carolina.\u201d Nowhere is it suggested in section 62-110.1(c) that the purpose of the proceeding is to issue directives which fundamentally alter a given utility\u2019s operations. Rather, we believe that the least-cost planning proceeding should bear a much closer resemblance to a legislative hearing, wherein a legislative committee gathers facts and opinions so that informed decisions may be made at a later time. Indeed, the very language of section 62-110.1(c), which requires the Commission to consider the analysis which results from the least-cost proceeding when acting upon a petition for the construction of a facility for the generation of electricity, appears to support this inference. In the instant case, however, no such petition was before the Commission and, therefore, the Commission was neither required nor even authorized, in the context of the proceedings in question, to issue the order which NCEMC sought.\nIf an intervenor desires the Commission to issue a mandatory order which will require a utility to take or to refrain from taking some specific substantive action, it may file a complaint pursuant to G.S. 62-73, which provides in relevant part as follows:\nComplaints may be made by the Commission on its own motion or by any person having an interest ... by petition or complaint in writing setting forth any act or thing done or omitted to be done by any public utility ... in violation of any provision of law or of any order or rule of the Commission, or that any rate, service, classification, rule, regulation or practice is unjust and unreasonable.\nN.C. Gen. Stat. \u00a7 62-73 (1989). By mentioning this alternative method of bringing concerns before the Commission, however, we do not mean to suggest that the issue of the real-time system demand signal is appropriately addressed to the Utilities Commission. We only mention section 62-73 to emphasize the point that the least-cost planning proceeding is not the appropriate occasion for the issuance of mandatory orders.\nIn the instant case, the Utilities Commission correctly recognized that the issue should be raised before FERC. As previously mentioned, exclusive jurisdiction over interstate wholesale electric power transactions is conferred upon FERC. NCEMC does not dispute FERC\u2019s authority to regulate the wholesale power transactions between it and CP&L. We shall, therefore, proceed under the assumption that NCEMC concedes this point. If the Commission were to order CP&L to provide its real-time system demand signal to NCEMC, issues which were within the exclusive province of FERC would be affected.\nIn this regard, CP&L contends, and NCEMC does not dispute, that an order requiring CP&L to provide its real-time system demand signal to NCEMC would implicate, at least to some extent, the wholesale rate at which CP&L sells NCEMC\u2019s member cooperatives electric energy. CP&L contends that this is because providing NCEMC with its real-time system demand signal would change \u201ca fundamental assumption\u201d upon which the wholesale rate tariffs (which CP&L charges NCEMC\u2019s member cooperatives) are based: that NCEMC and its member cooperatives would not have access to the real-time demand signal.\nAccording to CP&L, the monthly bills which it charges against NCEMC\u2019s member cooperatives in the CP&L area include both an energy component and a demand component. The energy component is based on a cooperative\u2019s total electric usage, as measured in kilowatthours, for the month, while the demand component is based primarily on the cooperative\u2019s demand, as measured in kilowatts (kW), during a one-hour period when CP&L\u2019s system demand reaches its peak for the month. CP&L further contends, and NCEMC does not dispute, that if NCEMC\u2019s cooperatives have access to CP&L\u2019s real-time system demand signal, then, by carefully observing fluctuations in system demand, the cooperatives could determine with considerable accuracy when the system reaches its monthly peak. With this information in hand, the cooperative could reduce its own demand during the period of peak demand, either by implementing a wide-scale demand reduction program such as that mentioned previously, or by purchasing a generator for use during the period of peak demand. In this way, CP&L argues, NCEMC\u2019s member cooperatives can create artificially low indications of their peak-hour demand, and thereby reduce the demand component of their monthly bills.\nWhile CP&L does not dispute that reducing peak-hour demand is a good idea, it does dispute that the manner in which this could be accomplished, were it to provide NCEMC with the real-time system signal, is fair. It is CP&L\u2019s position that, since its plants and facilities are constructed on the basis of its need for power over a broader period of time than the one-hour period of peak demand, the reduction of a cooperative\u2019s load for only one hour would have little or no effect on the cost of CP&L\u2019s system. As such, CP&L argues that, if it is ordered to supply NCEMC with the signal without a corresponding adjustment to the rate at which NCEMC and its member cooperatives are charged, the costs involved in meeting the expenses of expansion will be shifted to either CP&L\u2019s retail customers or to CP&L\u2019s shareholders.\nRegardless of the merits of CP&L\u2019s argument, it is obvious that the issuance of an order requiring CP&L to provide NCEMC with its real-time system demand signal would have some impact upon the fairness of the wholesale rates at which NCEMC\u2019s member cooperatives are sold electricity. For this reason, we are of the opinion that such an issue more appropriately is addressed to FERC. Accordingly, we conclude that the Utilities Commission properly refused to order CP&L to provide NCEMC with its real-time system demand signal. NCEMC\u2019s assignment of error on this point, therefore, is overruled.\nIII.\nIn its final assignment of error, NCEMC contends that the Commission exceeded its statutory authority when, in its 17 May 1990 order, it announced its intention to require NCEMC \u201cto participate in all future least-cost integrated resource planning proceedings\u201d once a rulemaking proceeding for that purpose could be held. Unless and until the Commission actually institutes a rulemaking proceeding which results in such a requirement, we can discern no justiciable issue or genuine controversy between the parties. As such, the issue is not ripe for our determination and we decline to address it.\nIV.\nFor the reasons discussed above, the order of the Utilities Commission is,\nAffirmed.\nJudges COZORT and ORR concur.",
        "type": "majority",
        "author": "WYNN, Judge."
      }
    ],
    "attorneys": [
      "Thomas J. Bolch, Brand & Leckie, by Wallace E. Brand and Donrita Y. Cottrell, and Milton Grossman, of Counsel, for appellant, North Carolina Electric Membership Corporation.",
      "H. Ray Starling, Jr., for appellee, Carolina Power & Light.",
      "Steve C. Griffith, Jr., William Larry Porter, Karol G. Page, and Kennedy, Covington, Lobdell & Hickman, by Myles E. Standish, for appellee, Duke Power Company.",
      "Gisele L. Rankin, for appellee, Public Staff \u2014 North Carolina Utilities Commission."
    ],
    "corrections": "",
    "head_matter": "STATE OF NORTH CAROLINA ex rel. UTILITIES COMMISSION; PUBLIC STAFF-NORTH CAROLINA UTILITIES COMMISSION; LACY H. THORNBURG, Attorney General; CAROLINA POWER & LIGHT COMPANY; DUKE POWER COMPANY; NANTAHALA POWER AND LIGHT COMPANY; NORTH CAROLINA CUSTOMERS ASSOCIATION, INC.; CAROLINA INDUSTRIAL GROUP FOR FAIR UTILITY RATES (CIGFUR-II); CONSERVATION COUNCIL OF NORTH CAROLINA; NORTH CAROLINA FAIR SHARE; NORTH CAROLINA CONSUMERS COUNCIL; NORTH CAROLINA SOLAR ENERGY ASSOCIATION; WESTERN NORTH CAROLINA ALLIANCE; SIERRA CLUB; JOCASSEE WATERSHED COALITION; ULTRASYSTEMS DEVELOPMENT CORPORATION; BLUE RIDGE ENVIRONMENTAL DEFENSE LEAGUE, INC.; and DAVID SPRINGER, Appellees v. NORTH CAROLINA ELECTRIC MEMBERSHIP CORPORATION, Appellant\nNo. 9010UC1166\n(Filed 21 January 1992)\n1. Energy \u00a7 21 (NCI4th)\u2014 least cost integrated resource plans \u2014 \u201cunqualified approval\u201d not given by Utilities Commission\nThere was no merit to NCEMC\u2019s contention that the Utilities Commission erred in granting its \u201cunqualified approval\u201d of least cost integrated resource plans submitted by Duke Power and CP&L, since the Commission found as fact only that the plans submitted were \u201creasonable for the purposes of [the] proceeding\u201d before it; that is, the plans were reasonable for analyzing the long-range needs for expansion of facilities for the generation of electricity in North Carolina; and the Commission made it expressly clear that the LCIRP proceedings were not meant to serve as a substitute for certification proceedings pursuant to N.C.G.S. \u00a7\u00a7 62-110 or 62-110.1(a).\nAm Jur 2d, Public Utilities \u00a7\u00a7 236, 270.\n2. Energy \u00a7 21 (NCI4th) \u2014 least cost integrated resource planning proceeding \u2014 consideration of testimony deferred \u2014issues properly before FERC\nNCEMC was not prejudiced by virtue of the Utilities Commission\u2019s decision finding Duke\u2019s and CP&L\u2019s LCIRPs reasonable, though the Commission deferred consideration of the testimony of two of NCEMC\u2019s witnesses, the substance of which NCEMC contended tended to show that the plans filed by Duke and CP&L were not least cost, since the same issues presented by the witnesses\u2019 testimony in this case were before the Federal Energy Regulatory Commission in a proceeding which was already underway; the testimony raised issues which were more appropriately directed to the attention of FERC, which has the exclusive authority to regulate interstate wholesale electric power transactions; and the Commission expressly left the witnesses\u2019 testimony open for consideration.\nAm Jur 2d, Public Utilities \u00a7 303.\n3. Energy \u00a7 21 (NCI4th)\u2014 least cost integrated resource planning proceeding \u2014 no forum for mandatory orders to utility companies\nThe newly-designed least cost integrated resource planning proceeding was not intended to provide an occasion for the issuance of mandatory orders requiring substantive changes in a given utility\u2019s operations. N.C.G.S. \u00a7 62-110.1(c).\nAm Jur 2d, Public Utilities \u00a7 270.\n4. Electricity \u00a7 3 (NCI3d)\u2014 method of operations \u2014 effect on fairness of wholesale rates \u2014 order requiring change of method\u2014 FERC appropriate forum\nThe issuance of an order requiring CP&L to provide NCEMC with its real-time system demand signal would have some impact upon the fairness of the wholesale rates at which NCEMC\u2019s member cooperatives are sold electricity, and such issue is therefore more appropriately addressed to FERC.\nAm Jur 2d, Public Utilities \u00a7 303.\nAPPEAL by the North Carolina Electric Membership Corporation from order entered 17 May 1990 by the North Carolina Utilities Commission.\nThomas J. Bolch, Brand & Leckie, by Wallace E. Brand and Donrita Y. Cottrell, and Milton Grossman, of Counsel, for appellant, North Carolina Electric Membership Corporation.\nH. Ray Starling, Jr., for appellee, Carolina Power & Light.\nSteve C. Griffith, Jr., William Larry Porter, Karol G. Page, and Kennedy, Covington, Lobdell & Hickman, by Myles E. Standish, for appellee, Duke Power Company.\nGisele L. Rankin, for appellee, Public Staff \u2014 North Carolina Utilities Commission."
  },
  "file_name": "0136-01",
  "first_page_order": 164,
  "last_page_order": 174
}