  "id": 4161600,
  "name": "D&R CONSTRUCTION CO., INC., Plaintiff v. BLANCHARD'S GROVE MISSIONARY BAPTIST CHURCH, an unincorporated association; TRUSTEES OF BLANCHARD'S GROVE MISSIONARY BAPTIST CHURCH; LEON HOLLEY, CHAIRMAN TRUSTEE; CURTIS HOLLEY, JR., TRUSTEE; SAMUEL EASTON, TRUSTEE; and BARBARA HOLLEY, TRUSTEE, Defendants and RBC CENTURA BANK, Additional Defendant",
  "name_abbreviation": "D&R Construction Co. v. Blanchard's Grove Missionary Baptist Church",
  "decision_date": "2008-10-21",
  "docket_number": "No. COA08-94",
  "first_page": "426",
  "last_page": "432",
  "citations": [
    {
      "type": "official",
      "cite": "193 N.C. App. 426"
    }
  ],
  "court": {
    "name_abbreviation": "N.C. Ct. App.",
    "id": 14983,
    "name": "North Carolina Court of Appeals"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [
    {
      "cite": "N.C. Gen. Stat. \u00a7 14569.3",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "pin_cites": [
        {
          "page": "(b)"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "N.C. Gen. Stat. \u00a7 14569.4",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "pin_cites": [
        {
          "page": "(c)"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "N.C. Gen. Stat. \u00a7 1-569.3",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "weight": 2,
      "opinion_index": 0
    },
    {
      "cite": "216 S.E.2d 456",
      "category": "reporters:state_regional",
      "reporter": "S.E.2d",
      "year": 1975,
      "pin_cites": [
        {
          "page": "457-58",
          "parenthetical": "citations omitted"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "26 N.C. App. 506",
      "category": "reporters:state",
      "reporter": "N.C. App.",
      "case_ids": [
        8553818
      ],
      "year": 1975,
      "pin_cites": [
        {
          "page": "508",
          "parenthetical": "citations omitted"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/nc-app/26/0506-01"
      ]
    },
    {
      "cite": "588 S.E.2d 575",
      "category": "reporters:state_regional",
      "reporter": "S.E.2d",
      "year": 2003,
      "pin_cites": [
        {
          "page": "577",
          "parenthetical": "citations omitted"
        }
      ],
      "opinion_index": 0
    },
    {
      "cite": "161 N.C. App. 488",
      "category": "reporters:state",
      "reporter": "N.C. App.",
      "case_ids": [
        8958700
      ],
      "year": 2003,
      "pin_cites": [
        {
          "page": "490-91",
          "parenthetical": "citations omitted"
        }
      ],
      "opinion_index": 0,
      "case_paths": [
        "/nc-app/161/0488-01"
      ]
    },
    {
      "cite": "N.C. Gen. Stat. \u00a7 1-567.2",
      "category": "laws:leg_statute",
      "reporter": "N.C. Gen. Stat.",
      "year": 2001,
      "opinion_index": 0
    }
  ],
  "analysis": {
    "cardinality": 558,
    "char_count": 14510,
    "ocr_confidence": 0.751,
    "pagerank": {
      "raw": 4.417441169658951e-08,
      "percentile": 0.2770574655124681
    },
    "sha256": "fa80fb3952e7413a01de96d9eb4671af8402c56d3e742412333d1ca18b97512a",
    "simhash": "1:ff3fa13c4a7fe7e3",
    "word_count": 2345
  },
  "last_updated": "2023-07-14T16:30:29.332614+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [
      "Judges McGEE and McCULLOUGH concur."
    ],
    "parties": [
      "D&R CONSTRUCTION CO., INC., Plaintiff v. BLANCHARD\u2019S GROVE MISSIONARY BAPTIST CHURCH, an unincorporated association; TRUSTEES OF BLANCHARD\u2019S GROVE MISSIONARY BAPTIST CHURCH; LEON HOLLEY, CHAIRMAN TRUSTEE; CURTIS HOLLEY, JR., TRUSTEE; SAMUEL EASTON, TRUSTEE; and BARBARA HOLLEY, TRUSTEE, Defendants and RBC CENTURA BANK, Additional Defendant"
    ],
    "opinions": [
      {
        "text": "STROUD, Judge.\nPlaintiff appeals order and judgment allowing defendants\u2019 \u201cMotion to Confirm and Enter Judgment on Arbitration Award\u201d and denying plaintiff\u2019s \u201cMotion to Vacate Arbitration Award and Demand for Trial De Novo.\u201d The dispositive issue before this Court is whether the arbitration was conducted pursuant to the correct law. For the following reasons, we affirm the order and judgment of the trial court.\nI. Background\nOn 3 June 2003, plaintiff and Blanchard Grove Missionary Baptist Church (\u201cChurch\u201d) by Leon Holley, Curtis Holley, Jr., and Barbara Holley entered into a \u201cContractual Agreement\u201d (\u201ccontract\u201d). The contract read in pertinent part,\nThe parties, Blanchard Grove and Trustees (\u201cBuyer(s)\u201d), and D&R Construction Co., Inc (\u201cContractor\u201d), in consideration for the promises and covenants made herein, agree that the Contractor shall build a new construction church sanctuary for the Owners, according to the terms set forth below:\n9. Arbitration: Any disagreement arising out of this Agreement or the application of any provisions thereof shall be submitted to an Arbitrator(s) not interested in the finances of the contract. The parties may agree on an Arbitrator, or may select one each and these two shall select a third. Any such arbitration award shall be binding and have the same weight and effect as a legal decision.\nDuring construction of the church building, a dispute developed between plaintiff and defendants regarding payment. Plaintiff filed liens on defendants\u2019 real property, and on 3 August 2004, plaintiff filed a verified \u201cCOMPLAINT, MOTION TO STAY PENDING ARBITRATION, MOTION TO APPOINT ARBITRATOR AND MOTION FOR PARTIAL SUMMARY JUDGMENT!.]\u201d (All caps in original.) In its complaint plaintiff brought claims for breach of contract, unjust enrichment, and a lien judgment on the property. Plaintiff also requested that the trial court stay the litigation pending arbitration, appoint an arbitrator, and grant partial summary judgment.\nOn 12 October 2004, defendants answered plaintiff\u2019s complaint alleging several defenses and counterclaiming for breach of contract. On 13 December 2004, plaintiff filed \u201cMOTIONS, REPLY TO COUNTERCLAIM, AFFIRMATIVE DEFENSES AND THIRD PARTY COMPLAINT[.]\u201d (All caps in original.) In July of 2005, RBC Centura Bank (\u201cRBC\u201d) filed a motion to intervene as a defendant and an answer to plaintiff\u2019s complaint.\nOn 3 March 2006, the trial court by consent order allowed RBC to intervene, stayed the action pending arbitration, ordered disputes to be submitted to arbitration \u201cin accordance with Section 9 of the June 3, 2003 \u2018Contractual Agreement\u2019 between D&R Construction Co., Inc. and Blanchard\u2019s Grove Missionary Baptist Church and Article 45C of Chapter 1 of the North Carolina General Statutesf,]\u201d appointed an arbitrator, and ordered costs of the arbitration to be split equally between plaintiff, the defendant Church, and RBC. Arbitration was held on 1 March 2007 and the arbitration decision was filed on 11 April 2007. The arbitration decision determined that plaintiff had breached its contract with defendants, and therefore plaintiff was not entitled to any recovery from defendants and its claims of lien were void. Based on plaintiffs breach, the arbitration award assessed damages in the amount of \u201c$62,422.56 with interest thereon at the rate of 8% per annum to run from February 14, 2004 until paid together with the costs of this action\u201d to be paid by plaintiff to defendants.\nOn 2 May 2007, defendants filed a motion for confirmation of the arbitration award and entry of judgment in accordance with the award (\u201cdefendants\u2019 motion for confirmation of the award\u201d). On 9 May 2007; plaintiff filed a \u201cDEMAND FOR TRIAL de NOVO ... and NOTICE OF SUBSTITUTION OF COUNSEL\u201d (\u201cplaintiff\u2019s motion for new trial\u201d) and a \u201cMOTION TO VACATE ARBITRATION AWARD & NOTICE OF SUBSTITUTION OF NEW COUNSEL\u201d (\u201cplaintiff\u2019s motion to vacate\u201d). (All caps in original.) On 22 May 2007, defendants filed a motion to deny and strike plaintiff\u2019s two motions and to impose sanctions (defendants\u2019 motion to deny\u201d). On 4 June 2007, a notice of hearing was filed regarding both of plaintiff\u2019s motions and defendants\u2019 motion to deny.\nOn 9 July 2007, a consent order was filed allowing plaintiff to substitute counsel and the trial court heard defendants\u2019 motion for confirmation of the award and both of plaintiff\u2019s motions. On 10 July 2007, the trial court entered its order which denied both of plaintiff\u2019s motions and allowed defendants\u2019 motion for confirmation of the award. Plaintiff appeals from the 10 July 2007 order. For the following reasons, we affirm the order and judgment of the trial court.\nII. Law Applied at Arbitration\nPlaintiff\u2019s first three arguments are all variations of the same issue: whether the arbitration was conducted pursuant to the correct law. Plaintiff first argues that \u201cthe trial court erred in refusing to hear any evidence from plaintiff on it\u2019s [sic] motion to vacate, including the testimony of a material witness present pursuant to subpoena, thereby violating plaintiff\u2019s substantive rights and preventing plaintiff\u2019s ability to establish a record for review.\u201d Plaintiff claims that its previous attorney, James Laurie (\u201cMr. Laurie\u201d), was present to testify regarding \u201cconfusion as which set of rules would apply\u201d at the arbitration. Plaintiff claims that this confusion arose because the construction contract was entered on 3 June 2003, when the\napplicable arbitration statute in effect . . . was the Uniform Arbitration Act, now repealed. N.C. Gen. Stat. \u00a7 1-567.2 (2001). The arbitration statute in effect at the time the matter was brought before the courts was the Revised Uniform Arbitration Act (\u201cRUAA\u201d), under Chapter 1, Article 45C of the North Carolina General Statutes. Because the parties\u2019 contract predated the RUAA, and because the contract itself did not clearly specify the scope and terms of the arbitration, and did not specify the applicable rules for arbitration, the parties had to supply these terms post-contract.\n\u201cThe law of contracts governs the issue of whether there exists an agreement to arbitrate. Accordingly, the party seeking arbitration must show that the parties mutually agreed to arbitrate their disputes.\u201d Burgess v. Jim Walter Homes, Inc., 161 N.C. App. 488, 490-91, 588 S.E.2d 575, 577 (2003) (citations omitted). However, in this case, plaintiff does not dispute that it agreed to submit the dispute to arbitration, and plaintiff did not appeal from the consent order which directed the case to arbitration. Plaintiff disputes only that it agreed to be bound by the Revised Uniform Arbitration Act, Article 45C, as opposed to the Uniform Arbitration Act, which was in effect at the time of entry of the construction contract.\nIn this case, the parties entered into two agreements to arbitrate: first, the construction contract in 2003, and second, the consent order in 2006. As plaintiff notes in its brief as to the specific rules to govern the arbitration, the \u201cparties had to supply these terms post-contract[,]\u201d and the parties did actually \u201csupply these terms\u201d in the consent order. Here the arbitration hearing was convened \u201cpursuant to the Order of the Court filed on March 3, 2006, and consented to by the Parties.\" The Uniform Arbitration Act which was in effect in 2003 was Article 45A of Chapter 1. The 3 March 2006 consent order requires the arbitration to be \u201cin accordance with . . . Article 45C of Chapter 1 of the North Carolina General Statutes.\u201d (Emphasis added.) The provisions of the order are clear and unambiguous. Any \u201cconfusion\u201d which an individual may have had about what rules would apply is not relevant, given the clear terms of the consent order. Martin v. Martin, 26 N.C. App. 506, 508, 216 S.E.2d 456, 457-58 (1975) (citations omitted) (\u201cA consent judgment must be construed in the same manner as a contract to ascertain the intent of the parties. Where the language of a contract is plain and unambiguous, the construction of the agreement is a matter of law; and the court may not ignore or delete any of its provisions, nor insert words into it, but must construe the contract as written, in the light of the undisputed evidence as to the custom, usage, and meaning of its terms.\u201d) We conclude that the trial court did not abuse its discretion in refusing to allow Mr. Laurie to testify as to the alleged \u201cconfusion\u201d as such testimony would be irrelevant. This argument is meritless.\nPlaintiffs next argument is closely akin to the previous argument in that plaintiff again claims there was confusion as to the applicable rules as \u201c[arbitrator Michael announced in open court that he would be applying the Rules for Court Ordered Arbitration in North Carolina\u201d instead of Article 45C of Chapter 1 of the North Carolina General Statutes. Plaintiff claims the arbitrator exceeded his authority \u201c[b]y acting contrary to the express authority conferred\u201d in the 3 March 2006 consent order. However, as we have already determined, the consent order directed that the arbitration be conducted pursuant to Article 45C of Chapter 1 of the North Carolina General Statutes. Plaintiff does not argue that the arbitrator failed to apply the provisions of Article 45C properly. This argument is also meritless.\nPlaintiff finally contends that the \u201cconfusion\u201d over which rules the arbitrator was applying resulted in \u201cno meeting of the minds as to the application of the appropriate rules.\u201d Again, a meeting of the minds as to the applicable rules is evidenced by the 3 March 2006 consent order which required Article 45C of Chapter 1 of the North Carolina General Statutes to govern the arbitration proceedings. Plaintiff has not appealed from the consent order and has not alleged that there was any defect in the entry of the consent order, and thus this argument is also meritless.\nIII. Conflicting Law\nLastly, plaintiff contends that N.C. Gen. Stat. \u00a7\u00a7 l-569.3(b) and - 569.4(c) are in conflict with each other and incapable of being read harmoniously.\nN.C. Gen. Stat. \u00a7 1-569.3 reads,\n(a) This Article governs an agreement to arbitrate made on or after January 1, 2004.\n(b) This Article governs an agreement to arbitrate made before January 1, 2004, if all parties to the agreement or to the arbitration proceeding agree in a record that this Article applies.\nN.C. Gen. Stat. \u00a7 1-569.3 (2003).\nN.C. Gen. Stat. \u00a7 14569.4(c) reads,\n(c) A party to an agreement to arbitrate or to an arbitration proceeding may not waive, or the parties shall not vary the effect of, the requirements of this section or G.S. l-569.3(a) .... Any waiver contrary to this section shall not be effective but shall not have the effect of voiding the agreement to arbitrate.\nN.C. Gen. Stat. \u00a7 l-569.4(c) (2003).\nPlaintiff contends, \u201cThe provision at N.C.G.S. \u00a7 l-569.3(b) allows for waiver of the provision at N.C.G.S. \u00a7 l-569.3(a). In contrast, the provision at N.C.G.S. \u00a7 l-569.4(a)(c) [sic] prohibits the variance or waiver of the terms in the provision found at N.C.G.S. \u00a7 l-569.3(a).\u201d We see no conflict between the two provisions. First, N.C. Gen. Stat. \u00a7 l-569.3(a) applies to agreements \u201cto arbitrate made on or after January 1, 2004[;]\u201d N.C. Gen. Stat. \u00a7 14569.3(b) applies to agreements \u201cto arbitrate made before January 1, 2004.\u201d N.C. Gen. Stat. \u00a7 l-569.3(a), (b) (emphasis added). Also, N.C. Gen. Stat. \u00a7 l-569.4(c) does not list \u00a7 l-569.3(b) as one of the \u201cnonwaivable\u201d provisions contained in Article 45C; it lists only subsection (a). See N.C. Gen. Stat. \u00a7 l-569(4)(c). In any event, the consent order to arbitrate in this case was entered after January 1, 2004; therefore N.C. Gen. Stat. \u00a7 l-569.3(b) is not applicable. Only N.C. Gen. Stat. \u00a7 l-569.3(a) applies, and the parties did not even attempt to waive any of the provisions of Article 45C, but instead expressly agreed to their application. This argument is meritless.\nIV. Conclusion\nFor the reasons as stated above, we deem all of plaintiffs arguments to be unsupported by the record and the law and without merit. We affirm the trial court order and judgment.\nAFFIRMED.\nJudges McGEE and McCULLOUGH concur.",
        "type": "majority",
        "author": "STROUD, Judge."
      }
    ],
    "attorneys": [
      "Ericka Young James, for plaintiff-appellant.",
      "Homthal, Riley, Ellis & Maland, L.L.R, by M.H. Hood Ellis and L. Phillip Homthal, III, for defendant-appellee."
    ],
    "corrections": "",
    "head_matter": "D&R CONSTRUCTION CO., INC., Plaintiff v. BLANCHARD\u2019S GROVE MISSIONARY BAPTIST CHURCH, an unincorporated association; TRUSTEES OF BLANCHARD\u2019S GROVE MISSIONARY BAPTIST CHURCH; LEON HOLLEY, CHAIRMAN TRUSTEE; CURTIS HOLLEY, JR., TRUSTEE; SAMUEL EASTON, TRUSTEE; and BARBARA HOLLEY, TRUSTEE, Defendants and RBC CENTURA BANK, Additional Defendant\nNo. COA08-94\n(Filed 21 October 2008)\n1. Arbitration and Mediation\u2014 motion to vacate \u2014 confusion over what rules would apply\nThe trial court did not err by allowing defendants\u2019 motion to confirm and enter judgment on an arbitration award and by denying plaintiff\u2019s motion to vacate the arbitration award and demand for trial de novo even though plaintiff contends the arbitration was not conducted pursuant to correct law because: (1) although the Uniform Arbitration Act which was in effect when the parties contracted in 2003 was Article 45A of Chapter 1, a 3 March 2006 consent order required the arbitration to be in accordance with Article 45C of the North Carolina General Statutes, and any confusion which an individual may have had about what rules would apply was not relevant given the clear terms of the consent order; (2) plaintiff did not argue that the arbitrator failed to apply the provisions of Article 45C properly; and (3) although plaintiff contends the confusion over which rules the arbitrator was applying resulted in no meeting of the minds as to the application of the appropriate rules, the consent order evidences otherwise, and plaintiff has not appealed from the consent order nor alleged that there was any defect in the entry of the consent order.\n2. Arbitration and Mediation\u2014 alleged conflict in statutes\u2014 inapplicable statute\nAlthough plaintiff contends in an arbitration case that N.C.G.S. \u00a7\u00a7 l-569.3(b) and -569.4(c) are in conflict with each other and incapable of being read harmoniously, there was no conflict between the two provisions, and in any event, N.C.G.S. \u00a7 l-569.3(b) was inapplicable when the consent order to arbitrate in the instant case was entered after 1 January 2004.\nAppeal by plaintiff from order and judgment entered 10 July 2007 by Judge Clifton W. Everett, Jr. in Superior Court, Gates County. Heard in the Court of Appeals 26 August 2008.\nEricka Young James, for plaintiff-appellant.\nHomthal, Riley, Ellis & Maland, L.L.R, by M.H. Hood Ellis and L. Phillip Homthal, III, for defendant-appellee."
  },
  "file_name": "0426-01",
  "first_page_order": 458,
  "last_page_order": 464
}