  "id": 11273918,
  "name": "McCORD v. SOUTHERN RAILWAY COMPANY",
  "name_abbreviation": "McCord v. Southern Railway Co.",
  "decision_date": "1902-06-13",
  "docket_number": "",
  "first_page": "491",
  "last_page": "493",
  "citations": [
    {
      "type": "official",
      "cite": "130 N.C. 491"
    }
  ],
  "court": {
    "name_abbreviation": "N.C.",
    "id": 9292,
    "name": "Supreme Court of North Carolina"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [
    {
      "cite": "121 N. C., 258",
      "category": "reporters:state",
      "reporter": "N.C.",
      "case_ids": [
        8652911
      ],
      "opinion_index": 0,
      "case_paths": [
        "/nc/121/0258-01"
      ]
    }
  ],
  "analysis": {
    "cardinality": 276,
    "char_count": 4150,
    "ocr_confidence": 0.386,
    "pagerank": {
      "raw": 4.03580807328026e-08,
      "percentile": 0.23915718638422548
    },
    "sha256": "55d375029f13d9841ad1040f7422ae62ff876b81f881c31e64591924e4cfbad3",
    "simhash": "1:2f397ea61d1c866d",
    "word_count": 733
  },
  "last_updated": "2023-07-14T15:31:43.301896+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "McCORD v. SOUTHERN RAILWAY COMPANY."
    ],
    "opinions": [
      {
        "text": "Clark, J.\nThe plaintiff was employed by the defendant to assist in digging a well 20 feet square for the use of its road. There was a cross-piece over said well, used as a cross-way by those in digging the well. The plaintiff objected that this cross-piece was not secure, whereupon the defendant\u2019s \u201cboss\u201d in charge of the work made a show of fixing said cross-piece, and assured plaintiff that said cross-piece was all right, in consequence of which assurance, and relying upon it, the plaintiff attempted to go out upon said cross-piece to turn off the steam jet, which was part of his duty; but said cross-piece having been insecurely fixed, it turned and threw into the well, whereby he was injured..\nAt the close of the plaintiff\u2019s evidence, and again at the close of all of the evidence, the defendant moved for a non-suit, and the refusal to do so is the ground of the defendant\u2019s first and third exceptions.\nThere was much evidence in support and in contradiction of the above, but as on this motion the evidence must.be taken most 'strongly in favor of the plaintiff, it is clear that the Court could not hold that there was no evidence sufficient to go to the jury. The plaintiff testified that it was his duty to turn off the steam jet, and the earth being banked, mud knee deep all around the piling except at the place where the crosspiece was laid, and that there was no appliance or means provided by the company to reach the jet except by going out on this cross-piece, which was provided for that purpose, and that he was careful to observe and test that cross-piece, and at his instance it was worked upon, and he was assured by the \u201cboss\u201d, that it had been made safe; that it was in fact an unsafe appliance, and he was injured in consequence. It being the plaintiff\u2019s duty to go out on the cross-piece, it was negligence in the defendant to give him an unsafe place and appliance for his work. Upon this evidence, the Court could not do otherwise than to submit the issues as to negligence and contributory negligence to the jury.\nTbe defendant put in evidence a paragraph of the plaintiff\u2019s complaint as an admission against him. Whereupon the Court allowed the plaintiff to put in evidence the other paragraphs of the complaint which referred to the same matter, and which he contended explained it. It is elementary that when part of a declaration or admission is put in evidence, the party making it has a right to have the whole of the declaration brought out. Whether it explains or modifies the other part already in evidence, is for the jury. This disposes - of the second exception.\nThe fourth exception is to \u201cgiving prayers asked by the plaintiff,\u201d but the case as settled by the Judge shows none, and that must govern, even if the appellant had set out the alleged prayers, which he does not. Patterson v. Mills, 121 N. C., 258, and other cases cited in Clark\u2019s Code (3d Ed.), page 762. There is no exception to the charge of the Court,, which, besides, is very full and clear, and entirely fair to the defendant.\nThe fifth and last exception is to the refusal of a new trial upon the foregoing exceptions.\nNo Error.",
        "type": "majority",
        "author": "Clark, J."
      }
    ],
    "attorneys": [
      "McCall & Nixon, for the plaintiff.",
      "George F. Bason, for the defendant."
    ],
    "corrections": "",
    "head_matter": "McCORD v. SOUTHERN RAILWAY COMPANY.\n(Filed June 13, 1902.)\n1. NEGLIGENCE \u2014 Contributory Negligence \u2014 Personal Injuries \u2014 Damges.\nThe evidence in tMs case as to negligence of railroad in injuring person wlio was assisting in digging a well for the railroad company, is sufficient to he submitted to the jury.\n2. EVIDENCE \u2014 Pleadings\u2014Complaint.\nWhere part of the complaint in an action is put in evidence, the party making the complaint is entitled to have the whole complaint introduced.\n3. APPEAL \u2014 Case on Appeal \u2014 Assignment of Error.\nIt will not he assumed that an assignment of error is a correct statement of facts therein recited, where such facts do not appear in the case stated hy the trial judge.\nActiON by W. E. McCord against the Southern Railway Company, heard by Judge W. A. Hohe and a jury, at July Term, 1901, of the Superior Court of Mecklenburg County. Erom a judgment for the plaintiff, the defendant appealed.\nMcCall & Nixon, for the plaintiff.\nGeorge F. Bason, for the defendant."
  },
  "file_name": "0491-01",
  "first_page_order": 529,
  "last_page_order": 531
}