  "id": 11269483,
  "name": "JONES v. WATER CO.",
  "name_abbreviation": "Jones v. Water Co.",
  "decision_date": "1905-05-16",
  "docket_number": "",
  "first_page": "383",
  "last_page": "384",
  "citations": [
    {
      "type": "official",
      "cite": "138 N.C. 383"
    }
  ],
  "court": {
    "name_abbreviation": "N.C.",
    "id": 9292,
    "name": "Supreme Court of North Carolina"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [
    {
      "cite": "135 N. C., 554",
      "category": "reporters:state",
      "reporter": "N.C.",
      "opinion_index": 0
    }
  ],
  "analysis": {
    "cardinality": 200,
    "char_count": 2860,
    "ocr_confidence": 0.416,
    "pagerank": {
      "raw": 4.621887471290392e-08,
      "percentile": 0.2901696199276483
    },
    "sha256": "302af330554ef47cdcb115ef84437614411fbff7225c6b7732c5d15296e64d65",
    "simhash": "1:cc002978b10ef1e5",
    "word_count": 501
  },
  "last_updated": "2023-07-14T14:59:46.048294+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "JONES v. WATER CO."
    ],
    "opinions": [
      {
        "text": "Clark, C. J.\nThis case was before us at a former term, 135 N. C., 554. On the second trial the court charged the jury: \u201cIt was the defendant\u2019s duty under its contract with the City of Durham to supply, at all times, water and pressure sufficient for the extinguishment of fires in said city.\u201d This was in accordance with what was said in our former opinion, in which it was further said that the provision as to furnishing more than five streams, thrown to \u201ca height of 100 feet in still air,\u201d upon four minutes\u2019 notice, was simply a test of'pressure and capacity to determine the rental which the city should pay. The test of the defendant\u2019s duty to the plaintiff was correctly stated, as above, by the judge and did not require four minutes\u2019 notice nor 100 feet of elevation. At all times it was the defendant\u2019s duty to furnish a supply of water and of course with adequate pressure to put out fires, for it was not a \u201csupply of water to extinguish fires,\u201d unless there was pressure sufficient to make the water available for that purpose. This was the measure of the defendant\u2019s duty, and not \u201c100 feet in still air.\u201d Water thrown to such height might more easily put out fires, but if the supply and pressure actually furnished were adequate (as the jury find), that was a compliance with the contract.\nThe case was properly submitted to the jury, and they have found that the defendant did its duty, as above specified. There are, numerous exceptions, but upon examination we deem them without merit and that they are npt such as require any further discussion. Whether the cause of the loss of the plaintiff\u2019s building was that the fire had gotten too great headway, or that the fire companies were not as efficient as usual, or because there was loss of time in putting on another stream during which delay the stream playing on the fire was allowed to \u201cdie down,\u201d or to whatever other causes, the jury have found under proper instructions .that the plaintiff\u2019s loss was not due to failure of the defendant to furnish water and 'pressure sufficient to extinguish fires. The defendant did not insure the plaintiff\u2019s house against fire.\nNo Error.",
        "type": "majority",
        "author": "Clark, C. J."
      }
    ],
    "attorneys": [
      "Manning & Foushee and Boone & Beade for the plaintiff.",
      "Winston & Bryant and Fuller & Fuller for the defendant."
    ],
    "corrections": "",
    "head_matter": "JONES v. WATER CO.\n(Filed May 16, 1905.)\nContract to Supply Water Construed \u2014 Fires.\nAn instraetion that \u201cit was the defendant\u2019s duty, under its contract with the City of Durham, to supply at all times water and pressure sufficient for the extinguishment of fires in said City\u201d correctly ^stated the test of the defendant\u2019s duty to the plaintiff as decided on the former appeal.\nActioN by R. M. Jones against Durham Water Company, beard by Judge B. B. Peebles and a jury at the January Term, 1905, of the Superior Court of Durham County. Erom a judgment for the defendant, the plaintiff appealed.\nManning & Foushee and Boone & Beade for the plaintiff.\nWinston & Bryant and Fuller & Fuller for the defendant."
  },
  "file_name": "0383-01",
  "first_page_order": 423,
  "last_page_order": 424
}