  "name": "J. C. NEAL, Jr., v. HAGEDORN CONSTRUCTION COMPANY et al.",
  "name_abbreviation": "Neal v. Hagedorn Construction Co.",
  "decision_date": "1926-10-27",
  "docket_number": "",
  "first_page": "816",
  "last_page": "818",
  "citations": [
    {
      "type": "official",
      "cite": "192 N.C. 816"
    }
  ],
  "court": {
    "name_abbreviation": "N.C.",
    "id": 9292,
    "name": "Supreme Court of North Carolina"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [
    {
      "cite": "175 N. C., 431",
      "category": "reporters:state",
      "reporter": "N.C.",
      "case_ids": [
        8659940
      ],
      "opinion_index": 0,
      "case_paths": [
        "/nc/175/0431-01"
      ]
    }
  ],
  "analysis": {
    "cardinality": 206,
    "char_count": 3309,
    "ocr_confidence": 0.446,
    "pagerank": {
      "raw": 4.03580807328026e-08,
      "percentile": 0.20727733547399868
    },
    "sha256": "e96f9ada75218af523d48ac4b60151ac14d4af67fa098489c88e13def3a1c854",
    "simhash": "1:8e711b40a2c53a73",
    "word_count": 543
  },
  "last_updated": "2023-07-14T21:52:38.190415+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "J. C. NEAL, Jr., v. HAGEDORN CONSTRUCTION COMPANY et al."
    ],
    "opinions": [
      {
        "text": "Pee Cueiam.\nDefendants assign as error the refusal of the court to sustain their exceptions to findings of fact by the referee. There was evidence at the hearing to sustain these findings of fact. The controversy between plaintiff and defendants was as to whether the construction company had expressly agreed to pay plaintiff for work which he had performed and which was included in a subcontract between the construction company and Wise & O\u2019Donnell, subcontractors. There was evidence tending to show that plaintiff declined to undertake this work at the request of the subcontractors, and agreed to do the work only after the construction company, at the request of the subcontractors, had agreed to pay for same direct to plaintiff, and not through the subcontractor. Defendants contended that the construction company agreed to make payment for the work to plaintiff, only on account of the subcontractors; that the construction company had overpaid the subcontractors and owed them nothing.\nThere was sharp conflict in the evidence as to the facts involved in the respective contentions of the parties; as there was evidence, however, to sustain the referee\u2019s findings which the judge approved, the assignments of error cannot be sustained. In Dumas v. Morrison, 175 N. C., 431, it is said, by Walker, J.: \u201cIt must be remembered that a judge of the Superior Court in reviewing a referee\u2019s report is not confined to the question whether there is any evidence to support his findings of fact, but he may also decide that while there is some such evidence, it does not preponderate in favor of the plaintiff, and thus find the facts contrary to those reported by the referee. The rule is otherwise in this Court, when a referee\u2019s report is under consideration. We do not review the judge\u2019s findings, if there is any evidence to support them, and we do not pass upon the weight of the evidence.\u201d\nUpon the findings of fact by the referee, approved by the judge, the Hagedorn Construction Company was primarily liable to plaintiff. Its agreement to pay for the work was not without consideration. It was obligated by its contract with the State Highway Commission to have this work done. Its agreement with plaintiff was made with, tbe consent, and indeed at tbe request, of tbe subcontractor. Assignments of error based upon exceptions to tbe refusal of tbe court to sustain tbeir exceptions to tbe conclusions of law of tbe referee, cannot be sustained. We find no error. Tbe judgment is\nAffirmed.",
        "type": "majority",
        "author": "Pee Cueiam."
      }
    ],
    "attorneys": [
      "G. Ed Taylor for plaintiff.",
      "O. D. Weeks for defendant."
    ],
    "corrections": "",
    "head_matter": "J. C. NEAL, Jr., v. HAGEDORN CONSTRUCTION COMPANY et al.\n(Filed 27 October, 1926.)\n1. Reference \u2014 Evidence\u2014Appeal and Error \u2014 Review.\nTbe Supreme Court will not on appeal review tbe findings of tbe referee, upon sufficient legal evidence, approved by tbe court.\n2. Contracts \u2014 Subcontracts\u2014Direct Promise to Pay \u2014 Considei'ation.\nTbe direct promise of a contractor to pay for work done for its subcontractor is supported by a consideration, and is enforceable.\nAppeal by defendants from Midyette, J'at January Term, ,1926, of BeuNswick. Affirmed.\nAction to recover for services rendered upon an express contract to pay for same.\nFrom judgment confirming the report of the referee, and in accordance therewith, defendants appealed to the Supreme Court.\nG. Ed Taylor for plaintiff.\nO. D. Weeks for defendant."
  },