  "id": 8632032,
  "name": "J. R. CHERRY v. CITY OF CHARLOTTE",
  "name_abbreviation": "Cherry v. City of Charlotte",
  "decision_date": "1933-11-22",
  "docket_number": "",
  "first_page": "837",
  "last_page": "838",
  "citations": [
    {
      "type": "official",
      "cite": "205 N.C. 837"
    }
  ],
  "court": {
    "name_abbreviation": "N.C.",
    "id": 9292,
    "name": "Supreme Court of North Carolina"
  },
  "jurisdiction": {
    "id": 5,
    "name_long": "North Carolina",
    "name": "N.C."
  },
  "cites_to": [],
  "analysis": {
    "cardinality": 227,
    "char_count": 3273,
    "ocr_confidence": 0.457,
    "sha256": "2bf2b3fc36873df5e0d8d127290ce3ba4df5398c5f8d571fa6a95a48e41ceb47",
    "simhash": "1:b6b2a089090743dd",
    "word_count": 601
  },
  "last_updated": "2023-07-14T16:12:31.066060+00:00",
  "provenance": {
    "date_added": "2019-08-29",
    "source": "Harvard",
    "batch": "2018"
  },
  "casebody": {
    "judges": [],
    "parties": [
      "J. R. CHERRY v. CITY OF CHARLOTTE."
    ],
    "opinions": [
      {
        "text": "Fiat ConiAM.\nThe plaintiff owned and constructed a water line and made provisions in such construction for taps to be made for the use of purchasers of lots in his subdivision. Moreover he constructed the line as he testified with the full knowledge that the city would run water through it and that it would charge for the water. There was evidence that the city had given one person permission to tap the line without the consent of plaintiff, and that the regular tapping fee was $65.00. The city denies that it has appropriated the property.\nAll phases of the case were submitted to the jury by the trial judge, and no error of law appears in the record.\nAffirmed.",
        "type": "majority",
        "author": "Fiat ConiAM."
      }
    ],
    "attorneys": [
      "J. F. Flowers and J. Louis Garter for plaintiff.",
      "IF. S. Blaheney and Bridges & Orr for defendant."
    ],
    "corrections": "",
    "head_matter": "J. R. CHERRY v. CITY OF CHARLOTTE.\n(Filed 22 November, 1933.)\nCivil ACTION, before Oglesby, J., at May Term, 1933, of Meck-LENBURG.\nThe plaintiff owned a tract of land on the Derita Road near the city of Charlotte. He developed this land into residential lots and to add to the desirability of the lots laid a water line about 3,500 feet long. The defendant city gave permission for the laying of such water line and furnished the specifications therefor and supervised the construction. The cost of the line was approximately $1,700, which was paid by the plaintiff.\nThe plaintiff testified as follows: \u201cHe arranged with Mr. Vest, superintendent of the water department of the city, that he would not take any one on my line without an order from me. He was to get an order from me and when I gave the order to him the tapping fee was to be paid to me, and I was to write an order to Mr. Vest after that, and be was then to connect tbe water and charge them for tbe water. . . . Tbe city made one connection that I know of for a man named Freeze . . . without my consent or without notifying me. . . . When I ran my water line out there I expected the city would run water through it and that it would charge for the water. . . . Provision was made in front of each lot so that you just had to tap on to get the water in there. . . .We just put a little T there so that they could get into the house. I do not contend that I still own the water line. I say the city owns it all. The city evidently owns it all. I say that because they permitted one man to tap on that they own it all now.\u201d\nUpon the foregoing evidence the plaintiff contended that as the city had permitted a man named Freeze to tap the water line owned by him that such tapping constituted an appropriation by the city of the whole line, and consequently the plaintiff brought suit for the value of his property.\nThe city denied that it had appropriated any property belonging to the plaintiff.\nThe following issues were submitted to the jury:\n1. \u201cWas the plaintiff the owner of the pipe line in March, 1930, as alleged in the complaint?\u201d\n2. \u201cDid the defendant appropriate to its own use any part of or all of plaintiff\u2019s pipe line in March, 1930, as alleged in the complaint?\u201d\n3. \u201cWhat was the value of the line or the part thereof appropriated by the defendant in March, 1930?\u201d\nThe first issue was answered \u201cYes\u201d; the second issue \u201cYes, one tapping,\u201d and the third issue \u201c$65.00.\u201d\nFrom judgment upon the verdict the plaintiff appealed.\nJ. F. Flowers and J. Louis Garter for plaintiff.\nIF. S. Blaheney and Bridges & Orr for defendant."
  },